4733-4735 N LEDGE AVE 91602

Certificate Information: 4733-4735 N LEDGE AVE 91602

Application / Permit
21014-10000-02397
Plan Check / Job No.
B21LA09059
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE/STORAGE ROOM TO ADU WITH AN ADDITION
Permit Issued
Issued on 10/27/2021
Issuing Office
Current Status
CofO Issued on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2021 APPLICANT
Assigned to Plan Check Engineer 5/17/2021 JOSEPH RAFOLS
Corrections Issued 5/17/2021 JOSEPH RAFOLS
Plan Check Approved 6/4/2021 SINA KHOSRAVI
Building Plans Picked Up 6/16/2021 APPLICANT
Issued 10/27/2021 APPLICANT
CofO in Progress 3/21/2022 MATT KELLERMAN
CofO in Progress 3/21/2022 MATT KELLERMAN
Permit Finaled 5/4/2022 MICHAEL SMITH
CofO Issued 5/4/2022 MICHAEL SMITH
Permit Finaled 5/4/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/21/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/21/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/24/2021 LEE GUILBEAUX

Contact Information

Contractor Globus Builder Inc; Lic. No.: 961380-B 1050 FLORENCE WAY      CAMPBELL, CA 950086606
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/23/2021 Corrections Issued THOMAS FINNILA
Deputy Drilled-In Anchors 11/24/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 11/30/2021 Partial Approval MATT KELLERMAN
BUILDING-Rough-Frame 12/6/2021 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/14/2021 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/28/2021 Partial Approval ASHLEY THOMPSON
HVAC-Rough 12/28/2021 Approved ASHLEY THOMPSON
PLUMBING-Rough 12/28/2021 Approved ASHLEY THOMPSON
Shower Pan 12/28/2021 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 1/4/2022 Approved CALEB MEISTER
HVAC-Rough 1/4/2022 Approved CALEB MEISTER
Insulation 1/4/2022 Corrections Issued CALEB MEISTER
Interior/Exterior Lathing 1/4/2022 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 1/4/2022 Approved CALEB MEISTER
Insulation 1/7/2022 Partial Inspection MISAEL ESPARZA
Wood Frame 1/7/2022 Corrections Issued MISAEL ESPARZA
Insulation 1/10/2022 Approved MATT KELLERMAN
Drywall Nailing 1/18/2022 Approved KRISTEN CAUSEY
Green Building Rough 1/18/2022 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 2/11/2022 Approved MATT KELLERMAN
Final 2/11/2022 Not Ready for Inspection MATT KELLERMAN
Footing/Foundation/Slab 2/11/2022 Approved MATT KELLERMAN
Green Building Final 2/11/2022 Not Ready for Inspection MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Approved MATT KELLERMAN
Smoke Detectors 2/11/2022 Not Ready for Inspection MATT KELLERMAN
Final 2/18/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 2/18/2022 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 2/18/2022 Approved JACK KARGODORIAN
Final 3/2/2022 Corrections Issued MATT KELLERMAN
Green Building Final 3/2/2022 Approved MATT KELLERMAN
Final 3/9/2022 Corrections Issued ARAM AVEDISIAN
Final 3/18/2022 OK to Issue CofO MATT KELLERMAN