4733-4735 N LEDGE AVE 91602
Certificate Information: 4733-4735 N LEDGE AVE 91602
- Application / Permit
- 21014-10000-02397
- Plan Check / Job No.
- B21LA09059
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE/STORAGE ROOM TO ADU WITH AN ADDITION
- Permit Issued
- Issued on 10/27/2021
- Issuing Office
- Current Status
- CofO Issued on 5/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2021 | JOSEPH RAFOLS |
| Corrections Issued | 5/17/2021 | JOSEPH RAFOLS |
| Plan Check Approved | 6/4/2021 | SINA KHOSRAVI |
| Building Plans Picked Up | 6/16/2021 | APPLICANT |
| Issued | 10/27/2021 | APPLICANT |
| CofO in Progress | 3/21/2022 | MATT KELLERMAN |
| CofO in Progress | 3/21/2022 | MATT KELLERMAN |
| Permit Finaled | 5/4/2022 | MICHAEL SMITH |
| CofO Issued | 5/4/2022 | MICHAEL SMITH |
| Permit Finaled | 5/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 5/21/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Globus Builder Inc; Lic. No.: 961380-B | 1050 FLORENCE WAY CAMPBELL, CA 950086606 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/23/2021 | Corrections Issued | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 11/24/2021 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 11/30/2021 | Partial Approval | MATT KELLERMAN |
| BUILDING-Rough-Frame | 12/6/2021 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 12/28/2021 | Partial Approval | ASHLEY THOMPSON |
| HVAC-Rough | 12/28/2021 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/28/2021 | Approved | ASHLEY THOMPSON |
| Shower Pan | 12/28/2021 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 1/4/2022 | Approved | CALEB MEISTER |
| HVAC-Rough | 1/4/2022 | Approved | CALEB MEISTER |
| Insulation | 1/4/2022 | Corrections Issued | CALEB MEISTER |
| Interior/Exterior Lathing | 1/4/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 1/4/2022 | Approved | CALEB MEISTER |
| Insulation | 1/7/2022 | Partial Inspection | MISAEL ESPARZA |
| Wood Frame | 1/7/2022 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 1/10/2022 | Approved | MATT KELLERMAN |
| Drywall Nailing | 1/18/2022 | Approved | KRISTEN CAUSEY |
| Green Building Rough | 1/18/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 2/11/2022 | Approved | MATT KELLERMAN |
| Final | 2/11/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Footing/Foundation/Slab | 2/11/2022 | Approved | MATT KELLERMAN |
| Green Building Final | 2/11/2022 | Not Ready for Inspection | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 2/11/2022 | SGSOV Approved | MATT KELLERMAN |
| Smoke Detectors | 2/11/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Final | 2/18/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 2/18/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 2/18/2022 | Approved | JACK KARGODORIAN |
| Final | 3/2/2022 | Corrections Issued | MATT KELLERMAN |
| Green Building Final | 3/2/2022 | Approved | MATT KELLERMAN |
| Final | 3/9/2022 | Corrections Issued | ARAM AVEDISIAN |
| Final | 3/18/2022 | OK to Issue CofO | MATT KELLERMAN |