3549 S OCEAN VIEW AVE 90066
Certificate Information: 3549 S OCEAN VIEW AVE 90066
- Application / Permit
- 21014-10000-02368
- Plan Check / Job No.
- B21LA08954
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert rear detached garage to ADU. 2nd level to remain as rec. room
- Permit Issued
- Issued on 8/13/2021
- Issuing Office
- Current Status
- CofO Issued on 11/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2021 | JOE VO |
| Corrections Issued | 5/21/2021 | JOE VO |
| Applicant returned to address corrections | 7/23/2021 | JOE VO |
| Plan Check Approved | 8/10/2021 | JOE VO |
| Issued | 8/13/2021 | APPLICANT |
| CofO in Progress | 11/18/2021 | KENNETH NAGLE |
| Permit Finaled | 11/18/2021 | KENNETH NAGLE |
| CofO Issued | 11/18/2021 | KENNETH NAGLE |
| Permit Finaled | 11/18/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 5/26/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 5/26/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2021 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 7/16/2021 | GREGORY HOERNER |
Contact Information
| Architect | Yung,, Paul H; Lic. No.: NA28869 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/20/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/30/2021 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2021 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 8/30/2021 | Corrections Issued | EVAN COOPER |
| Insulation | 8/30/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 8/30/2021 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 9/7/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 9/7/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 9/7/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 9/7/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/7/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Special/Order Compliance | 9/7/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/13/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 9/13/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 9/13/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/13/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 9/13/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 9/13/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 9/16/2021 | Corrections Issued | KENNETH NAGLE |
| PLUMBING-Rough | 9/16/2021 | Corrections Issued | KENNETH NAGLE |
| ELECTRICAL-Rough | 9/22/2021 | Corrections Issued | KENNETH NAGLE |
| Insulation | 9/22/2021 | Not Ready for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 9/22/2021 | Approved | KENNETH NAGLE |
| ELECTRICAL-Rough | 9/27/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/22/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 10/22/2021 | Approved | JOHNNY MIRANDA |
| Final | 10/22/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 10/22/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 10/22/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 10/22/2021 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 10/22/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 10/22/2021 | Approved | JOHNNY MIRANDA |
| Final | 11/2/2021 | Conditional Approval | JOHNNY MIRANDA |
| HVAC-Final | 11/2/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 11/2/2021 | Approved | JOHNNY MIRANDA |