4912 S 7TH AVE 90043
Certificate Information: 4912 S 7TH AVE 90043
- Application / Permit
- 21014-10000-02365
- Plan Check / Job No.
- B21LA08950
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT FIRST FLOOR OF EXISTING 2-STORY REC. ROOM TO AN ADU. ADD FOYER AT FIRST FLOOR. REC. ROOM REMODEL AT 2ND FLOOR.
- Permit Issued
- Issued on 11/9/2022
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2021 | JOE VO |
| Corrections Issued | 5/14/2021 | JOE VO |
| Applicant returned to address corrections | 9/10/2021 | JOE VO |
| Plan Check Approved | 11/12/2021 | JOE VO |
| Issued | 11/9/2022 | APPLICANT |
| CofO in Progress | 8/29/2024 | ANTHONY EGSON |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2021 | JEANIE LAM |
| Sewer availability | Cleared | 11/22/2021 | JEANIE LAM |
Contact Information
| Contractor | Nagura Construction Corp; Lic. No.: 947170-B | PO BOX 412337 LOS ANGELES, CA 90041 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 4/10/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 4/10/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 5/3/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Underground Mechanical | 5/3/2023 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 5/19/2023 | No Access for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/23/2023 | Corrections Issued | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 6/23/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/3/2023 | Approved | ANTHONY EGSON |
| Pre-Inspection | 7/24/2023 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/5/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 9/5/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Approved | ANTHONY EGSON |
| Green Building Rough | 9/5/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 9/5/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 9/5/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 9/5/2023 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | ANTHONY EGSON |
| Green Building Rough | 9/12/2023 | Approved | ANTHONY EGSON |
| HVAC-Rough | 9/12/2023 | Approved | ANTHONY EGSON |
| Insulation | 9/26/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 10/11/2023 | Approved | ANTHONY EGSON |
| Gas Test | 11/20/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 2/2/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 2/2/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 2/2/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 2/2/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 2/2/2024 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 2/2/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 2/2/2024 | Approved | ANTHONY EGSON |
| Final | 2/15/2024 | Partial Inspection | MICHAEL LEWIS |
| Green Building Final | 2/15/2024 | Approved | MICHAEL LEWIS |
| Final | 8/21/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 8/28/2024 | OK to Issue CofO | ANTHONY EGSON |