5604 E IRVINGTON PL 90042
Certificate Information: 5604 E IRVINGTON PL 90042
- Application / Permit
- 21014-10000-02363
- Plan Check / Job No.
- B21LA08947
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTING THE EXISTING GARAGE TO AN ADU WITH AN ADDITION (1-STORY)
- Permit Issued
- Issued on 8/19/2021
- Issuing Office
- Current Status
- CofO Issued on 3/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2021 | CARLOS MONTES |
| Corrections Issued | 5/18/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 6/3/2021 | CARLOS MONTES |
| Plan Check Approved | 7/6/2021 | CARLOS MONTES |
| Issued | 8/19/2021 | APPLICANT |
| CofO in Progress | 2/24/2022 | CRAIG VAUGHAN |
| Permit Finaled | 3/2/2022 | DEROLD HAUFF |
| CofO Issued | 3/2/2022 | DEROLD HAUFF |
| Permit Finaled | 3/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 5/24/2021 | TERRI OSBORNE |
| Address approval | Cleared | 5/26/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 5/26/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 5/27/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2021 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 6/14/2021 | BRIAN MILLER |
| HPOZ | Cleared | 7/1/2021 | KATIE DEBIASE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/30/2021 | Partial Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 9/28/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/28/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/28/2021 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 10/1/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/22/2021 | Not Ready for Inspection | DANIEL GONZALEZ |
| ELECTRICAL-Rough | 10/22/2021 | Not Ready for Inspection | DANIEL GONZALEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2021 | Partial Approval | DANIEL GONZALEZ |
| HVAC-Rough | 10/22/2021 | Not Ready for Inspection | DANIEL GONZALEZ |
| PLUMBING-Rough | 10/22/2021 | Not Ready for Inspection | DANIEL GONZALEZ |
| ELECTRICAL-Rough | 10/26/2021 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 10/26/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/26/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/1/2021 | Approved | COREY HUPP |
| HVAC-Rough | 11/1/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 11/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/12/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Shower Pan | 11/12/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/18/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 11/18/2021 | Partial Approval | OSVALDO PARAMO |
| Shower Pan | 11/18/2021 | Approved | OSVALDO PARAMO |
| Insulation | 11/23/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 11/23/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Drywall Nailing | 12/1/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 12/1/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 1/31/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 1/31/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 1/31/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 1/31/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 1/31/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 2/15/2022 | Corrections Issued | CRAIG VAUGHAN |
| Final | 2/15/2022 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 2/15/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 2/15/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 2/15/2022 | SGSOV Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 2/23/2022 | Approved | CRAIG VAUGHAN |
| Final | 2/23/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| Gas Test | 2/23/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 2/23/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 2/23/2022 | Approved | CRAIG VAUGHAN |