8401 S CROYDON AVE 90045
Certificate Information: 8401 S CROYDON AVE 90045
- Application / Permit
- 21014-10000-02337
- Plan Check / Job No.
- B21LA08828
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND INTERIOR REMODEL OF EXISTING SFD
- Permit Issued
- Issued on 6/30/2021
- Issuing Office
- Current Status
- CofO Issued on 7/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | STARR CHEN |
| Corrections Issued | 5/29/2021 | STARR CHEN |
| Quality Review Completed | 6/3/2021 | JASON HEALEY |
| Building Plans Picked Up | 6/7/2021 | APPLICANT |
| Plan Check Approved | 6/30/2021 | STARR CHEN |
| Issued | 6/30/2021 | APPLICANT |
| CofO in Progress | 7/25/2022 | ANDREW NAVE |
| Permit Finaled | 7/26/2022 | KENNETH NAGLE |
| CofO Issued | 7/26/2022 | KENNETH NAGLE |
| Permit Finaled | 7/26/2022 | KENNETH NAGLE |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/7/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2021 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 6/22/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | N A N D C O Llc; Lic. No.: 1044615-B | 4836 FULTON AVE SHERMAN OAKS, CA 91423 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/23/2021 | Conditional Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 8/11/2021 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/13/2021 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 8/13/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 8/13/2021 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2021 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 8/23/2021 | Approved | BRENDAN LOONEY |
| Pre-Inspection | 9/24/2021 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 11/29/2021 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 12/10/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/3/2022 | Not Ready for Inspection | BOBBY KEY |
| Green Building Rough | 1/3/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 1/3/2022 | Partial Approval | BOBBY KEY |
| Wood Frame | 1/3/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2022 | Approved | JOHN KAYON |
| BUILDING-Rough-Frame | 1/31/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 1/31/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Approved | BOBBY KEY |
| Green Building Rough | 1/31/2022 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 1/31/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 1/31/2022 | Approved | BOBBY KEY |
| Shower Pan | 1/31/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 2/15/2022 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 2/15/2022 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 2/15/2022 | Not Ready for Inspection | BOBBY KEY |
| Wood Frame | 2/15/2022 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 2/22/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 2/22/2022 | Approved | BOBBY KEY |
| Green Building Rough | 2/22/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 2/22/2022 | Approved | BOBBY KEY |
| Insulation | 2/28/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 3/7/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 5/13/2022 | Partial Approval | BOBBY KEY |
| Final | 5/13/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 5/13/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 5/13/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 5/13/2022 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/13/2022 | SGSOV Not Ready | BOBBY KEY |
| Service/Power Release | 5/13/2022 | Approved | BOBBY KEY |
| Smoke Detectors | 5/13/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 5/25/2022 | Corrections Issued | BOBBY KEY |
| Final | 5/25/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 5/25/2022 | Approved | BOBBY KEY |
| HVAC-Final | 5/25/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 5/25/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/25/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 5/25/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 6/3/2022 | Approved | BOBBY KEY |
| Final | 6/3/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 6/3/2022 | Approved | BOBBY KEY |
| Final | 7/25/2022 | OK to Issue CofO | ANDREW NAVE |