7508 N JAMIESON AVE 91335

Certificate Information: 7508 N JAMIESON AVE 91335

Application / Permit
21014-10000-02309
Plan Check / Job No.
B21LA08753
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-PLAN: CONVERT GARAGE TO ADU AND ADDITION PER LAMC PER LAMC 12.22 A.33(c) AND (d) and PER WFPP
Permit Issued
Issued on 9/28/2021
Issuing Office
Current Status
CofO Issued on 5/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2021 APPLICANT
Assigned to Plan Check Engineer 5/11/2021 CRYSTEL MAALOUF
Corrections Issued 5/11/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 7/20/2021 CRYSTEL MAALOUF
Plan Check Approved 8/6/2021 CRYSTEL MAALOUF
Issued 9/28/2021 APPLICANT
CofO in Progress 5/13/2022 VINCENT HANLEY
CofO Issued 5/21/2022 MICHAEL SMITH
Permit Finaled 5/21/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/14/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/17/2021 CARLOS AGUILERA
Sewer availability Cleared 5/17/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 8/1/2021 ROBERT DUFF

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/3/2021 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 11/12/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 1/3/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 1/3/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 1/3/2022 Corrections Issued DAVID SCANTLIN
BUILDING-Rough-Frame 1/13/2022 Approved VINCENT HANLEY
Green Building Rough 1/13/2022 Approved VINCENT HANLEY
HVAC-Rough 1/13/2022 Approved VINCENT HANLEY
PLUMBING-Rough 1/13/2022 Approved VINCENT HANLEY
Insulation 1/24/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/24/2022 Approved VINCENT HANLEY
Shower Pan 1/24/2022 Approved VINCENT HANLEY
Drywall Nailing 2/3/2022 Approved JAVIER RAMOS JR
Sewer 2/3/2022 Approved JAVIER RAMOS JR
Underground Mechanical 2/3/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 4/13/2022 Approved VINCENT HANLEY
Final 4/13/2022 Corrections Issued VINCENT HANLEY
Green Building Final 4/13/2022 Approved VINCENT HANLEY
PLUMBING-Final 4/13/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/13/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 4/13/2022 Approved VINCENT HANLEY
Final 5/13/2022 OK to Issue CofO VINCENT HANLEY