839 N ENCHANTED WAY 90272
Certificate Information: 839 N ENCHANTED WAY 90272
- Application / Permit
- 21014-10000-02286
- Plan Check / Job No.
- B21LA08625
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND MAJOR REMODEL TO EXISTING SFD W GARAGE
- Permit Issued
- Issued on 5/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | MICHAEL LOPEZ |
| Corrections Issued | 6/3/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 6/7/2021 | WING SUEN |
| Building Plans Picked Up | 6/17/2021 | APPLICANT |
| Applicant returned to address corrections | 10/13/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 12/9/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 1/14/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/4/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 3/10/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 4/14/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 4/22/2022 | STARR CHEN |
| Applicant returned to address corrections | 5/6/2022 | STARR CHEN |
| Plan Check Approved | 5/11/2022 | STARR CHEN |
| Issued | 5/13/2022 | APPLICANT |
| CofO in Progress | 10/29/2024 | EVAN COOPER |
| CofO Issued | 10/30/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/30/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Hold | Cleared | 6/7/2021 | JASON SHEETS |
| BHO/Hillside ordinance | Cleared | 7/1/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 7/1/2021 | DINAH GARIN |
| Sewer availability | Cleared | 7/1/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2021 | DINAH GARIN |
| Coastal Zone | Cleared | 10/1/2021 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 11/23/2021 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 11/23/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 4/14/2022 | MATTHEW JENKINS |
| BHO/Hillside ordinance | Cleared | 5/2/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 5/2/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 5/2/2022 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 5/11/2022 | STARR CHEN |
Contact Information
| Contractor | Todd Lance Construction Inc; Lic. No.: 692325-B | 3087 RENEE CT SIMI VALLEY, CA 93065 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
| Engineer | Rogers,, Jerome Alan; Lic. No.: L5336 | 135 N SAN GABRIEL AVE 100 SAN GABRIEL, CA 91775 |
| Engineer | Tucker,, Keith D; Lic. No.: GE841 | PO BOX 8133 HUNTINGTON BEACH, CA 92615 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/24/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/3/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/22/2022 | Approved | ANDREW NAVE |
| Underground Mechanical | 6/22/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2022 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2022 | Conditional Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/27/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 9/27/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 9/27/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 9/28/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 10/13/2022 | Approved | EVAN COOPER |
| HVAC-Rough | 10/13/2022 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 10/20/2022 | Approved | BRENDAN LOONEY |
| Wood Frame | 10/20/2022 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/24/2022 | Partial Approval | BRENDAN LOONEY |
| Deputy Wood Construction | 10/24/2022 | Approved | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 10/24/2022 | Corrections Issued | BRENDAN LOONEY |
| Deputy Wood Construction | 10/28/2022 | Conditional Approval | MICHAEL PELHAM |
| Interior/Exterior Lathing | 11/21/2022 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 12/9/2022 | Approved | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 12/9/2022 | Approved | BRENDAN LOONEY |
| Wood Frame | 12/9/2022 | Approved | BRENDAN LOONEY |
| Insulation | 12/14/2022 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 12/20/2022 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 1/10/2023 | Partial Approval | BRENDAN LOONEY |
| Shower Pan | 1/10/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 7/10/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 7/10/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 7/10/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 7/26/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 8/11/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 8/11/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 8/31/2023 | Approved | EVAN COOPER |
| Final | 8/31/2023 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 8/31/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/31/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 8/31/2023 | Approved | EVAN COOPER |
| Final | 3/7/2024 | Not Ready for Inspection | EVAN COOPER |
| Final | 10/29/2024 | OK to Issue CofO | EVAN COOPER |