6800 W SUNSET BLVD 90028

Certificate Information: 6800 W SUNSET BLVD 90028

Application / Permit
21014-10000-02268
Plan Check / Job No.
B21LA08591
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANE OF USE FROM FLOWER SHOP TO RESTAURANT WITH DRIVE-THR, OUTDOOR SEATING (116 SF) AND ADDITION PER ZA-2021-2125-CU "COMPLY WITH DEPARTMENT ORDER effective date 05/19/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"CEIS Case Number is 957147.
Permit Issued
Issued on 9/1/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 AUNG SOE
Corrections Issued 7/6/2021 AUNG SOE
Quality Review Completed 7/6/2021 EUGENE BARBEAU
Building Plans Picked Up 7/8/2021 APPLICANT
Disabled Access Plans Picked Up 11/19/2021 APPLICANT
Green Plans Picked Up 4/12/2022 APPLICANT
Applicant returned to address corrections 8/26/2022 AUNG SOE
Plan Check Approved 9/1/2022 AUNG SOE
Issued 9/1/2022 APPLICANT
TCO Issued (Expire Date: 11-15-2023) 5/19/2023 TED RIES
CofO in Progress 8/29/2025 ADAM BURGESS
CofO Issued 8/29/2025 ADAM BURGESS
Permit Finaled 8/29/2025 ADAM BURGESS

Permit Application Clearance Information

Hold Cleared 5/19/2021 JASON SHEETS
Green Code Cleared 9/9/2021 AARON COSTA
DAS Clearance Cleared 9/13/2021 AUNG SOE
Eng Process Fee Ord 176,300 Cleared 9/13/2021 JEANIE LAM
Sewer availability Cleared 9/13/2021 JEANIE LAM
Hydrant and Access approval Cleared 9/15/2021 KURT CORRAL
Food Service Establishment Cleared 10/7/2021 PAWAN VERMA
Driveway location Cleared 1/14/2022 MOHAMMAD HASAN
Miscellaneous Cleared 3/22/2022 RUBEN VASQUEZ
ZA Case Cleared 3/22/2022 RUBEN VASQUEZ
ZA Case Cleared 3/22/2022 RUBEN VASQUEZ
ZA Case Cleared 3/22/2022 RUBEN VASQUEZ
Trees in Parkway Cleared 4/12/2022 ADALBERTO VERA
"D" conditions Cleared 4/21/2022 RUBEN VASQUEZ
Comm Cor/Mini-Mall Cleared 4/21/2022 RUBEN VASQUEZ
Comm Cor/Mini-Mall Cleared 4/21/2022 RUBEN VASQUEZ
Comm Cor/Mini-Mall Cleared 4/21/2022 RUBEN VASQUEZ
Drive-through fast food Cleared 4/21/2022 RUBEN VASQUEZ
Miscellaneous Cleared 4/21/2022 RUBEN VASQUEZ
ZA Case Cleared 4/21/2022 RUBEN VASQUEZ
Redevelopment Project Area Cleared 5/9/2022 SUSAN WONG
Low Impact Development Cleared 7/21/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/2/2022 JEANETTE VONG
Highway dedication Cleared 8/3/2022 JEANIE LAM
Permit Cleared 8/25/2022 JEANIE LAM
Food establishment approval Cleared 8/26/2022 LACDHS APPROVED

Contact Information

Architect Beauter,, William L; Lic. No.: C29188 2664 LACY STREET STUDIO A      LOS ANGELES, CA 90031
Contractor Terra Nova Industries; Lic. No.: 460854-B 1607 TICE VALLEY BLVD      WALNUT CREEK, CA 94595
Engineer Karimoto,, Derek Haruo; Lic. No.: C42356 24655 ACROPOLIS DR      MISSION VIEJO, CA 92691
Engineer Schroeder,, Mark Ernest; Lic. No.: S4110 16969 VON KARMAN AVE 240      IRVINE, CA 92606
Landscape Architect Baldovin,, James Eugene; Lic. No.: LA4176 3195 C AIRPORT LOOP DRIVE      COSTA MESA, CA 92626

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/20/2022 Approved JONATHAN QUACH
Footing/Foundation/Slab 9/21/2022 Partial Approval JONATHAN QUACH
Deputy Reinf. Concrete 9/28/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 9/29/2022 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 10/7/2022 Partial Inspection JONATHAN QUACH
Insulation 10/11/2022 Partial Approval JONATHAN QUACH
Wood Frame 10/11/2022 Partial Inspection JONATHAN QUACH
Green Building Rough 10/13/2022 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 10/13/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/20/2022 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 10/21/2022 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 11/7/2022 Not Ready for Inspection JONATHAN QUACH
Wood Frame 11/7/2022 Not Ready for Inspection JONATHAN QUACH
Final 11/9/2022 Not Ready for Inspection ALFREDO LOPEZ
Footing/Foundation/Slab 11/9/2022 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 11/9/2022 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 11/9/2022 Not Ready for Inspection ALFREDO LOPEZ
Footing/Foundation/Slab 11/23/2022 Partial Approval RONALD JIMENEZ
Deputy Reinf. Concrete 11/30/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 12/9/2022 Partial Approval JONATHAN QUACH
Green Building Rough 12/9/2022 Not Ready for Inspection JONATHAN QUACH
Wood Frame 12/9/2022 Partial Approval JONATHAN QUACH
Deputy Wood Construction 12/20/2022 Conditional Approval TIMOTHY POWELL
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Conditional Approval VAHE KELEDJIAN
Deputy Steel/Welding 12/22/2022 Conditional Approval TIMOTHY POWELL
Deputy Steel/Welding 12/23/2022 Conditional Approval TIMOTHY POWELL
Wood Frame 12/28/2022 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 12/29/2022 Not Ready for Inspection RONALD JIMENEZ
Green Building Rough 12/29/2022 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 12/29/2022 Partial Approval RONALD JIMENEZ
Deputy Steel/Welding 1/4/2023 Conditional Approval TIMOTHY POWELL
Deputy Steel/Welding 1/6/2023 Approved TIMOTHY POWELL
Drywall Nailing 1/6/2023 Partial Approval TIMOTHY POWELL
Drywall Nailing 1/10/2023 Approved RONALD JIMENEZ
Deputy Steel/Welding 1/12/2023 Conditional Approval TIMOTHY POWELL
Deputy Steel/Welding 1/13/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/17/2023 Conditional Approval RONALD JIMENEZ
Deputy Steel/Welding 1/18/2023 Conditional Approval RONALD JIMENEZ
Deputy Steel/Welding 1/19/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/20/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/23/2023 Conditional Approval TIMOTHY POWELL
Deputy Steel/Welding 1/24/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/25/2023 Conditional Approval TIMOTHY POWELL
Deputy Steel/Welding 1/26/2023 Conditional Approval TIMOTHY POWELL
Deputy Steel/Welding 1/27/2023 Conditional Approval TIMOTHY POWELL
Deputy Steel/Welding 1/31/2023 Partial Approval TIMOTHY POWELL
Deputy Steel/Welding 2/1/2023 Conditional Approval TIMOTHY POWELL
Deputy Steel/Welding 2/3/2023 Conditional Approval RONALD JIMENEZ
Deputy Steel/Welding 2/6/2023 Conditional Approval TIMOTHY POWELL
Deputy Steel/Welding 2/7/2023 Conditional Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 2/7/2023 Partial Approval RONALD JIMENEZ
Deputy Steel/Welding 2/8/2023 Conditional Approval RONALD JIMENEZ
Reinforced Concrete Frame 2/8/2023 Partial Approval RONALD JIMENEZ
Deputy Steel/Welding 2/9/2023 Conditional Approval RONALD JIMENEZ
Deputy Steel/Welding 2/10/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 2/15/2023 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 2/17/2023 Partial Approval RONALD JIMENEZ
Deputy Steel/Welding 3/1/2023 Conditional Approval RONALD JIMENEZ
Special/Order Compliance 3/1/2023 Approved RONALD JIMENEZ
Deputy Steel/Welding 3/2/2023 Conditional Approval MICHAEL ROSENBERG
Interior/Exterior Lathing 3/10/2023 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Not Ready RONALD JIMENEZ
Structural Steel Frame 3/14/2023 Partial Approval RONALD JIMENEZ
T-Bar Ceiling 3/14/2023 Partial Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV Not Ready RONALD JIMENEZ
Structural Steel Frame 3/17/2023 Partial Inspection RONALD JIMENEZ
Deputy Steel/Welding 3/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 3/24/2023 Conditional Approval RONALD JIMENEZ
Deputy Steel/Welding 3/29/2023 Conditional Approval RONALD JIMENEZ
Footing/Foundation/Slab 3/29/2023 Not Ready for Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Not Ready RONALD JIMENEZ
Structural Steel Frame 3/29/2023 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 3/30/2023 Partial Inspection RONALD JIMENEZ
Deputy Steel/Welding 3/31/2023 Conditional Approval RONALD JIMENEZ
Deputy Steel/Welding 4/3/2023 Conditional Approval RONALD JIMENEZ
Footing/Foundation/Slab 4/3/2023 Partial Approval RONALD JIMENEZ
Insulation 4/3/2023 Partial Inspection RONALD JIMENEZ
Footing/Foundation/Slab 4/17/2023 Partial Approval RONALD JIMENEZ
Final 5/9/2023 Partial Inspection RONALD JIMENEZ
Footing/Foundation/Slab 5/9/2023 Approved RONALD JIMENEZ
Green Building Final 5/9/2023 Approved RONALD JIMENEZ
Green Building Rough 5/9/2023 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 5/9/2023 Approved RONALD JIMENEZ
Wood Frame 5/9/2023 Approved RONALD JIMENEZ
Special/Order Compliance 5/31/2023 Approved RONALD JIMENEZ
Special/Order Compliance 10/18/2023 Approved RONALD JIMENEZ
Special/Order Compliance 5/7/2024 Partial Inspection TIMOTHY POWELL
Final 7/31/2025 OK to Issue CofO TIMOTHY POWELL