3651-3653 S MEIER ST 90066
Certificate Information: 3651-3653 S MEIER ST 90066
- Application / Permit
- 21014-10000-02261
- Plan Check / Job No.
- B21LA08586
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD GROUND FLOOR & SECOND STORY ADDITION TO (E) 1-STORY SFD. (N) COVERED DECK. CONVERSION OF (E) 1-CAR GARAGE INTO JADU STRUCTURAL REMODEL PROVIDED PER PLAN.
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Current Status
- CofO Issued on 5/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/17/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 6/29/2021 | JASON HEALEY |
| Building Plans Picked Up | 7/8/2021 | APPLICANT |
| Applicant returned to address corrections | 4/28/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 9/6/2022 | MAHNAZ NOURHASHEMI |
| Issued | 9/7/2022 | APPLICANT |
| CofO in Progress | 5/9/2025 | JESUS PINEDA |
| CofO Issued | 5/13/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/13/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/26/2021 | TIMOTHY POWELL |
| Address approval | Cleared | 7/28/2021 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 7/28/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 7/28/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2021 | DENNIS BRAGIN |
| Miscellaneous | Cleared | 5/3/2022 | RAYMOND MUGAMBWA |
| Specific Plan | Cleared | 7/11/2022 | VALERIA CEJA |
| GPI Written Notices | Cleared | 7/22/2022 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Tm Design Build; Lic. No.: 1068098-B | 27475 YNEZ RD #349 TEMECULA, CA 92591 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/26/2022 | Not Ready for Inspection | HERBERT GIRON |
| Pre-Inspection | 10/26/2022 | Partial Inspection | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 12/9/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 12/23/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 1/12/2023 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/20/2023 | Partial Approval | JESUS RODRIGUEZ |
| Underground Mechanical | 3/20/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 3/30/2023 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 3/30/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/30/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 3/30/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/11/2023 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 7/11/2023 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/11/2023 | Partial Approval | JESUS RODRIGUEZ |
| Wood Frame | 7/11/2023 | Partial Approval | JESUS RODRIGUEZ |
| Insulation | 7/14/2023 | Partial Approval | JESUS PINEDA |
| Sewer | 7/19/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 7/19/2023 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/31/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/31/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 7/31/2023 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/7/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 9/21/2023 | Partial Approval | HERBERT GIRON |
| Shower Pan | 9/21/2023 | Approved | HERBERT GIRON |
| Deck | 9/25/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Insulation | 9/25/2023 | Partial Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/29/2023 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 11/8/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 11/8/2023 | Partial Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/8/2023 | Partial Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 11/17/2023 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 11/17/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/22/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 11/30/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 12/7/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 12/7/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 12/7/2023 | Approved | HERBERT GIRON |
| Deck | 2/22/2024 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 5/30/2024 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 5/30/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/5/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 6/5/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Final | 8/23/2024 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 8/23/2024 | Not Ready for Inspection | JESUS PINEDA |
| Gas Test | 9/6/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 9/6/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Approved | JESUS PINEDA |
| Sewer | 9/6/2024 | Approved | JESUS PINEDA |
| Final | 11/4/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 11/4/2024 | Approved | JESUS PINEDA |
| Smoke Detectors | 11/4/2024 | Approved | JESUS PINEDA |
| Final | 5/9/2025 | OK to Issue CofO | JESUS PINEDA |