2236 N RICHELIEU AVE 90032

Certificate Information: 2236 N RICHELIEU AVE 90032

Application / Permit
21014-10000-02256
Plan Check / Job No.
B21LA08577
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO REAR OF RESIDENCE AND ENCLOSURE OF EXISTING PORTION OF FRONT PORCH. TOTAL ADDITION IS 421 SF. ADDING ONE ADDITIONAL BEDROOM AND BATHROOM, A NEW POWDER ROOM AND LAUNDRY. REMODELING OF EXISTING KITCHEN AND EXISTING BATHROOM. REMODEL AREA IS 300 SF. REFRAME ENTIRE ROOF
Permit Issued
Issued on 6/2/2022
Issuing Office
Current Status
CofO Issued on 12/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2021 APPLICANT
Assigned to Plan Check Engineer 5/7/2021 JOSEPH RAFOLS
Corrections Issued 5/7/2021 JOSEPH RAFOLS
Building Plans Picked Up 5/10/2021 APPLICANT
Plan Check Approved 5/27/2022 DANIEL SANJUAN
Issued 6/2/2022 APPLICANT
CofO in Progress 12/4/2023 SCOTT FINNILA
CofO Issued 12/5/2023 DEROLD HAUFF
Permit Finaled 12/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/29/2022 KIRK LINKLATER
Roof/Waste drainage to street Cleared 5/12/2022 CINDY QI
Watercourse Cleared 5/12/2022 TERRY PHAN
Eng Process Fee Ord 176,300 Cleared 5/16/2022 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Phan,, Phillip Trung Tri; Lic. No.: C76425 641 S ALMIRANTE DR      WEST COVINA, CA 91791

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/22/2022 Corrections Issued AMY COLIN
Pre-Inspection 7/26/2022 Corrections Issued AMY COLIN
Footing/Foundation/Slab 7/29/2022 Conditional Approval AMY COLIN
BUILDING-Rough-Frame 1/13/2023 Conditional Approval AMY COLIN
ELECTRICAL-Rough 1/13/2023 Corrections Issued AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 1/13/2023 Conditional Approval AMY COLIN
Green Building Rough 1/13/2023 Not Ready for Inspection AMY COLIN
HVAC-Rough 1/13/2023 Approved AMY COLIN
PLUMBING-Rough 1/13/2023 Corrections Issued AMY COLIN
Wood Frame 1/13/2023 Corrections Issued AMY COLIN
Insulation 2/6/2023 Corrections Issued AMY COLIN
Interior/Exterior Lathing 2/6/2023 Partial Approval AMY COLIN
Insulation 2/13/2023 Approved RUBEN SALAS
Drywall Nailing 2/21/2023 Approved AMY COLIN
Green Building Rough 2/21/2023 Approved AMY COLIN
Interior/Exterior Lathing 4/18/2023 Approved AMY COLIN
Shower Pan 4/18/2023 Approved AMY COLIN
BUILDING-Rough-Frame 11/17/2023 Approved OSVALDO PARAMO
ELECTRICAL-Final 11/17/2023 Corrections Issued OSVALDO PARAMO
Final 11/17/2023 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 11/17/2023 Approved OSVALDO PARAMO
HVAC-Final 11/17/2023 Approved OSVALDO PARAMO
PLUMBING-Final 11/17/2023 Approved OSVALDO PARAMO
ELECTRICAL-Final 11/30/2023 Approved AMY COLIN
Final 11/30/2023 OK to Issue CofO AMY COLIN
Green Building Final 11/30/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 11/30/2023 SGSOV Approved AMY COLIN
Service/Power Release 11/30/2023 Approved AMY COLIN
Smoke Detectors 11/30/2023 Approved AMY COLIN