822-822 1/2 E 79TH ST 90001

Certificate Information: 822-822 1/2 E 79TH ST 90001

Application / Permit
21014-10000-02253
Plan Check / Job No.
B21LA08543
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition and Conversion of Garage to ADU per 12.22A.33(c) and (d).
Permit Issued
Issued on 7/22/2021
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2021 APPLICANT
Assigned to Plan Check Engineer 5/10/2021 HERNAN ARREOLA
Corrections Issued 5/10/2021 HERNAN ARREOLA
Applicant returned to address corrections 5/18/2021 HERNAN ARREOLA
Applicant returned to address corrections 5/21/2021 HERNAN ARREOLA
Plan Check Approved 5/31/2021 HERNAN ARREOLA
Issued 7/22/2021 APPLICANT
CofO in Progress 7/14/2022 LILIANA PORTILLO
Permit Finaled 7/23/2022 DEROLD HAUFF
CofO Issued 7/23/2022 DEROLD HAUFF
Permit Finaled 7/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/20/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 5/20/2021 JEANIE LAM
Sewer availability Cleared 5/20/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/25/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/9/2021 Approved SABAS ALONSO
Footing/Foundation/Slab 9/16/2021 No Access for Inspection DAVID FEILER
Footing/Foundation/Slab 9/22/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 12/2/2021 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 12/2/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/2/2021 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 12/6/2021 Conditional Approval SHAVONNE ESPINOZA
BUILDING-Rough-Frame 12/8/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/8/2021 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 12/8/2021 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 12/8/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/22/2021 Corrections Issued ADAM ESCOTO
Interior/Exterior Lathing 12/22/2021 Partial Approval ADAM ESCOTO
BUILDING-Rough-Frame 12/27/2021 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 1/11/2022 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 1/14/2022 Approved JOSEPH MCGARRY
Insulation 1/14/2022 Approved JOSEPH MCGARRY
Drywall Nailing 1/25/2022 Corrections Issued LILIANA PORTILLO
Drywall Nailing 1/31/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 1/31/2022 Approved LILIANA PORTILLO
Shower Pan 1/31/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 4/26/2022 Corrections Issued LILIANA PORTILLO
HVAC-Final 4/26/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/26/2022 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 4/26/2022 Approved LILIANA PORTILLO
Final 4/29/2022 Corrections Issued HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 4/29/2022 SGSOV Not Ready HORACE FULTZ
ELECTRICAL-Final 5/6/2022 Approved LILIANA PORTILLO
Final 5/6/2022 Corrections Issued LILIANA PORTILLO
HVAC-Final 5/6/2022 Approved LILIANA PORTILLO
PLUMBING-Final 5/6/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/6/2022 SGSOV Approved LILIANA PORTILLO
Final 6/30/2022 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 6/30/2022 Approved LILIANA PORTILLO
Final 7/13/2022 OK to Issue CofO LILIANA PORTILLO