140 E 107TH ST 90003

Certificate Information: 140 E 107TH ST 90003

Application / Permit
21014-10000-02252
Plan Check / Job No.
B21LA08542
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan PROPOSED ADDITION TO EXISTING DETACHED GARAGE TO CREATE AN ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 12/27/2021
Issuing Office
Current Status
CofO Issued on 9/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2021 APPLICANT
Assigned to Plan Check Engineer 5/11/2021 MICHAEL LOPEZ
Corrections Issued 5/11/2021 MICHAEL LOPEZ
Applicant returned to address corrections 5/18/2021 MICHAEL LOPEZ
Applicant returned to address corrections 6/30/2021 MICHAEL LOPEZ
Applicant returned to address corrections 7/29/2021 MICHAEL LOPEZ
Applicant returned to address corrections 8/20/2021 MICHAEL LOPEZ
Applicant returned to address corrections 8/27/2021 MICHAEL LOPEZ
Applicant returned to address corrections 11/23/2021 MICHAEL LOPEZ
Applicant returned to address corrections 12/3/2021 MICHAEL LOPEZ
Applicant returned to address corrections 12/8/2021 MICHAEL LOPEZ
Plan Check Approved 12/14/2021 MICHAEL LOPEZ
Issued 12/27/2021 APPLICANT
CofO in Progress 9/12/2022 ALIZAH MAYAGOITIA
CofO in Progress 9/13/2022 DONALD CRICHLOW
CofO in Progress 9/15/2022 ALIZAH MAYAGOITIA
Permit Finaled 9/30/2022 DEROLD HAUFF
CofO Issued 9/30/2022 DEROLD HAUFF
Permit Finaled 9/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/12/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/13/2021 CELINA MORENO
Low Impact Development Cleared 11/3/2021 KHAING AYE
Roof/Waste drainage to street Cleared 11/4/2021 CELINA MORENO
Sewer availability Cleared 11/4/2021 CELINA MORENO
Watercourse Cleared 11/18/2021 TERRY PHAN

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2022 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 1/27/2022 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 1/28/2022 Corrections Issued EUGENE CASSIDY
Special/Order Compliance 1/28/2022 Partial Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/22/2022 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 3/4/2022 Corrections Issued JOHN KLARIN
Excavation/Setback/Form/Re-Bar 3/9/2022 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/15/2022 Not Ready for Inspection JOHN KLARIN
HVAC-Rough 4/15/2022 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 4/15/2022 Not Ready for Inspection JOHN KLARIN
Wood Frame 4/15/2022 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 4/18/2022 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 4/18/2022 Approved JOHN KLARIN
HVAC-Rough 4/18/2022 Corrections Issued JOHN KLARIN
PLUMBING-Rough 4/18/2022 Corrections Issued JOHN KLARIN
HVAC-Rough 4/25/2022 Approved JOHN KLARIN
PLUMBING-Rough 4/25/2022 Approved JOHN KLARIN
Wood Frame 4/25/2022 Approved JOHN KLARIN
Insulation 4/28/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 4/28/2022 Approved JOHN KLARIN
Drywall Nailing 5/5/2022 Approved ALIZAH MAYAGOITIA
Gas Test 5/10/2022 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/10/2022 Conditional Approval ALIZAH MAYAGOITIA
Shower Pan 5/10/2022 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/13/2022 Approved ALIZAH MAYAGOITIA
Shower Pan 5/13/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/27/2022 Approved JOHN KLARIN
Final 7/27/2022 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 7/27/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Approved JOHN KLARIN
Smoke Detectors 7/27/2022 Approved JOHN KLARIN
Final 8/23/2022 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Final 9/12/2022 Approved ALIZAH MAYAGOITIA
Final 9/12/2022 Partial Approval ALIZAH MAYAGOITIA
HVAC-Final 9/12/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 9/12/2022 Approved ALIZAH MAYAGOITIA
Final 9/13/2022 Corrections Issued ALIZAH MAYAGOITIA
Final 9/15/2022 OK to Issue CofO ALIZAH MAYAGOITIA