147 E 120TH ST #147 main 90061

Certificate Information: 147 E 120TH ST #147 main 90061

Application / Permit
21014-10000-02250
Plan Check / Job No.
B21LA08540
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan. ADDITION TO EXISTING 1 STORY SFD TO 2 STORY SFD
Permit Issued
Issued on 1/27/2023
Issuing Office
Current Status
Issued on 1/27/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/6/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 CRYSTEL MAALOUF
Corrections Issued 6/22/2021 CRYSTEL MAALOUF
Quality Review Completed 7/1/2021 WING SUEN
Applicant returned to address corrections 8/25/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 11/17/2022 CRYSTEL MAALOUF
Plan Check Approved 1/26/2023 CRYSTEL MAALOUF
Issued 1/27/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/10/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/29/2022 WALLIE JONG
Hydrant and Access approval Cleared 3/30/2022 KURT CORRAL
Sewer availability Cleared 4/20/2022 WALLIE JONG
Community Plan Implem. Overlay Cleared 5/26/2022 HELEN JADALI

Contact Information

Contractor Owner-Builder       ,
Engineer Graciano,, Daniel Banuelos; Lic. No.: C57297 1340 N MURRAY ST      BANNING, CA 92220

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/12/2023 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 5/16/2023 Approved JOHN KLARIN
Footing/Foundation/Slab 5/16/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 7/13/2023 Partial Approval JOHN KLARIN
PLUMBING-Rough 7/13/2023 Partial Approval JOHN KLARIN
Insulation 7/18/2023 Partial Approval JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 10/10/2023 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 8/20/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 8/20/2024 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 8/20/2024 No Access for Inspection BEN MOLSTAD
PLUMBING-Rough 8/20/2024 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 9/18/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 9/18/2024 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 9/24/2024 Approved BEN MOLSTAD
PLUMBING-Rough 9/24/2024 Approved BEN MOLSTAD
BUILDING-Rough-Frame 9/26/2024 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Corrections Issued BEN MOLSTAD
HVAC-Final 9/26/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 9/26/2024 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 10/22/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Approved ANTHONY EGSON
HVAC-Rough 10/22/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 11/13/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Approved ANTHONY EGSON
HVAC-Rough 11/13/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/3/2024 Approved ANTHONY EGSON
Insulation 12/10/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/20/2024 Partial Inspection ANTHONY EGSON
Interior/Exterior Lathing 3/10/2025 Partial Approval ANTHONY EGSON
Shower Pan 3/10/2025 Approved ANTHONY EGSON
Drywall Nailing 7/17/2025 Approved JOHN KLARIN