11248 W RYE ST 91602

Certificate Information: 11248 W RYE ST 91602

Application / Permit
21014-10000-02225
Plan Check / Job No.
B21LA08413
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**eplan** CONVERT EXISTING 337 SQ. FT. DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 6/8/2021
Issuing Office
Current Status
CofO Issued on 8/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2021 APPLICANT
Assigned to Plan Check Engineer 5/5/2021 MICHAEL LOPEZ
Corrections Issued 5/5/2021 MICHAEL LOPEZ
Applicant returned to address corrections 5/14/2021 MICHAEL LOPEZ
Applicant returned to address corrections 5/21/2021 MICHAEL LOPEZ
Applicant returned to address corrections 5/25/2021 MICHAEL LOPEZ
Plan Check Approved 6/1/2021 MICHAEL LOPEZ
Issued 6/8/2021 APPLICANT
CofO in Progress 3/24/2022 DAVID MATSON
Permit Finaled 8/25/2022 DANIEL ORRANTE
CofO Issued 8/25/2022 DANIEL ORRANTE
Permit Finaled 8/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/7/2021 GABRIEL ROBLES
Sewer availability Cleared 5/7/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/8/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: NA5900       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/14/2021 Partial Inspection THOMAS FINNILA
Rough-Elec/Plmb/HVAC 7/21/2021 Partial Approval THOMAS FINNILA
Pre-Inspection 7/30/2021 Approved THOMAS FINNILA
Pre-Inspection 8/23/2021 Approved THOMAS FINNILA
Deputy Drilled-In Anchors 9/8/2021 Approved THOMAS FINNILA
Footing/Foundation/Slab 9/8/2021 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 9/10/2021 Partial Inspection THOMAS FINNILA
Footing/Foundation/Slab 9/16/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 9/24/2021 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 10/1/2021 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 10/8/2021 Partial Approval CALEB MEISTER
Sewer 10/8/2021 Approved CALEB MEISTER
Sewer 10/22/2021 No Access for Inspection THOMAS FINNILA
PLUMBING-Rough 10/26/2021 Corrections Issued CALEB MEISTER
PLUMBING-Rough 10/28/2021 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 11/17/2021 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 11/17/2021 Partial Approval THOMAS FINNILA
Wood Frame 11/17/2021 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 11/30/2021 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 11/30/2021 Corrections Issued THOMAS FINNILA
Insulation 11/30/2021 Corrections Issued THOMAS FINNILA
MERV13>=Rough 11/30/2021 Approved THOMAS FINNILA
Deputy Wood Construction 12/2/2021 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 12/7/2021 Approved THOMAS FINNILA
Wood Frame 12/7/2021 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 12/15/2021 Partial Approval THOMAS FINNILA
Drywall Nailing 12/28/2021 Corrections Issued DEANDRE HOFFMAN
Drywall Nailing 1/4/2022 Not Ready for Inspection CALEB MEISTER
Drywall Nailing 1/10/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 3/1/2022 Approved THOMAS FINNILA
Green Building Final 3/1/2022 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 3/1/2022 Approved THOMAS FINNILA
Smoke Detectors 3/1/2022 Not Ready for Inspection THOMAS FINNILA
Final 3/11/2022 Partial Approval THOMAS FINNILA
Green Building Final 3/11/2022 Approved THOMAS FINNILA
MERV13>=Final 3/11/2022 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Approved THOMAS FINNILA
Smoke Detectors 3/11/2022 Approved THOMAS FINNILA
ELECTRICAL-Final 3/17/2022 Approved DAVID MATSON
Final 3/24/2022 OK to Issue CofO DAVID MATSON