3751 S HILLCREST DR 90016

Certificate Information: 3751 S HILLCREST DR 90016

Application / Permit
21014-10000-02223
Plan Check / Job No.
B21LA08407
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW DECK AND ADDITION (165 SF) TO (E) SFD (1-STORY)
Permit Issued
Issued on 6/3/2021
Issuing Office
Current Status
CofO Issued on 5/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2021 APPLICANT
Assigned to Plan Check Engineer 5/6/2021 CARLOS MONTES
Corrections Issued 5/6/2021 CARLOS MONTES
Applicant returned to address corrections 5/24/2021 CARLOS MONTES
Plan Check Approved 5/26/2021 CARLOS MONTES
Issued 6/3/2021 APPLICANT
CofO in Progress 3/11/2023 ANTHONY EGSON
Permit Finaled 5/23/2023 DEROLD HAUFF
Permit Finaled 5/23/2023 DEROLD HAUFF
CofO Issued 5/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/14/2021 ROSA SILVA
Roof/Waste drainage to street Cleared 5/14/2021 ROSA SILVA

Contact Information

Contractor Precision Design & Build Inc; Lic. No.: 1036946-B       ,
Engineer Bareng,, Jenn Tamayo; Lic. No.: C79168 21301 ERWIN ST #427      WOODLAND HILLS, CA 91367

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/25/2021 Conditional Approval JOHN HAMILTON
Footing/Foundation/Slab 7/1/2021 Approved FREDDIE RIVERA
Insulation 8/3/2021 Partial Approval ADAM ESCOTO
Wood Frame 8/30/2021 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 11/10/2021 Partial Inspection ANTHONY EGSON
PLUMBING-Rough 11/10/2021 Partial Approval ANTHONY EGSON
PLUMBING-Rough 11/15/2021 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/14/2021 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/17/2021 Approved ANTHONY EGSON
Interior/Exterior Lathing 1/6/2022 Partial Approval HORACE FULTZ
BUILDING-Rough-Frame 1/12/2022 Corrections Issued AMY COLIN
Green Building Rough 1/12/2022 Not Ready for Inspection AMY COLIN
BUILDING-Rough-Frame 1/24/2022 Approved ANTHONY EGSON
Green Building Rough 1/24/2022 Approved ANTHONY EGSON
Insulation 1/31/2022 Approved ANTHONY EGSON
Drywall Nailing 2/9/2022 Approved ALEJANDRO DE ARTOLA
Shower Pan 2/16/2022 Corrections Issued ANTHONY EGSON
Shower Pan 2/23/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 3/3/2022 Approved ANTHONY EGSON
Final 5/19/2022 Conditional Approval ANTHONY EGSON
Green Building Final 5/19/2022 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Approved ANTHONY EGSON
Smoke Detectors 5/19/2022 Approved ANTHONY EGSON
Final 1/24/2023 Corrections Issued ANTHONY EGSON
Final 3/14/2023 Corrections Issued ANTHONY EGSON