2657 W LOCKSLEY PL 90039

Certificate Information: 2657 W LOCKSLEY PL 90039

Application / Permit
21014-10000-02211
Plan Check / Job No.
B21LA08355
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODLE AND 2ND STORY ADDITON TO (E) 1-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 6/28/2021
Issuing Office
Current Status
Issued on 6/28/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/4/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 DANIEL YIP
Corrections Issued 5/25/2021 DANIEL YIP
Quality Review Completed 6/1/2021 KEN GILL
Building Plans Picked Up 6/2/2021 APPLICANT
Applicant returned to address corrections 6/25/2021 DANIEL YIP
Plan Check Approved 6/28/2021 DANIEL YIP
Issued 6/28/2021 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/2/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 6/4/2021 CECILIO NAVARRO
Sewer availability Cleared 6/4/2021 CECILIO NAVARRO
Grading Pre-Inspection Cleared 6/16/2021 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Durand,, Paul Henri; Lic. No.: S4222 611 N G ST      OXNARD, CA 93030

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/27/2021 Corrections Issued THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 9/30/2021 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 9/30/2021 Not Ready for Inspection THOMAS LOGRASSO
Deputy Reinf. Concrete 10/12/2021 Partial Approval RUBEN SALAS
Pre-Inspection 11/29/2021 Partial Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 5/3/2022 Partial Inspection THOMAS LOGRASSO
Green Building Rough 5/3/2022 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Rough 5/3/2022 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 6/14/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 6/20/2022 Not Ready for Inspection JEFFREY MEAD
Green Building Rough 6/20/2022 Not Ready for Inspection JEFFREY MEAD
MERV13>=Rough 6/20/2022 Not Ready for Inspection JEFFREY MEAD
Rough-Elec/Plmb/HVAC 6/20/2022 Not Ready for Inspection JEFFREY MEAD
Rough-Elec/Plmb/HVAC 6/20/2022 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 7/8/2022 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 7/8/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 8/1/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 8/1/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 8/1/2022 Approved THOMAS LOGRASSO
Insulation 8/25/2022 Conditional Approval THOMAS LOGRASSO
Deck 9/8/2022 Partial Approval THOMAS LOGRASSO
Shower Pan 9/8/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 9/23/2022 Partial Approval THOMAS LOGRASSO
Drywall Nailing 10/20/2022 Approved THOMAS LOGRASSO
Green Building Rough 10/20/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 10/20/2022 Approved THOMAS LOGRASSO
HVAC-Rough 12/1/2022 Approved THOMAS LOGRASSO