816 1/2 S SPAULDING AVE 90036
Certificate Information: 816 1/2 S SPAULDING AVE 90036
- Application / Permit
- 21014-10000-02208
- Plan Check / Job No.
- B21LA08349
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EXISTING 2-CAR GARAGE TO E CONVERTED INTO AN ADU. NEW ADDITION TO THE PROPOSED ADU, NEW CONCRETE WALL
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 6/5/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 7/27/2021 | JESSE VIDUYA |
| Building Plans Picked Up | 8/5/2021 | APPLICANT |
| Plan Check Approved | 5/2/2022 | KHUONG TRUONG |
| Issued | 5/2/2022 | APPLICANT |
| CofO in Progress | 10/11/2023 | SCOTT FINNILA |
| Permit Finaled | 10/11/2023 | DEROLD HAUFF |
| CofO Issued | 10/11/2023 | DEROLD HAUFF |
| Permit Finaled | 10/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2021 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 9/30/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2021 | THOMAS LANG |
| Sewer availability | Cleared | 10/1/2021 | THOMAS LANG |
| HPOZ | Cleared | 1/12/2022 | CHRISTINA PARK |
| Construction near power lines | Cleared | 2/8/2022 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 2/9/2022 | DWAYNE LAURENT |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2022 | Corrections Issued | ADAM ESCOTO |
| BUILDING-Rough-Frame | 10/3/2023 | Approved | SCOTT FINNILA |
| Drywall Nailing | 10/3/2023 | Approved | SCOTT FINNILA |
| Final | 10/3/2023 | Corrections Issued | SCOTT FINNILA |
| Final | 10/3/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 10/3/2023 | Approved | SCOTT FINNILA |
| Green Building Final | 10/3/2023 | Approved | SCOTT FINNILA |
| Green Building Rough | 10/3/2023 | Approved | SCOTT FINNILA |
| METHANE-Barrier | 10/3/2023 | Approved | SCOTT FINNILA |
| METHANE-Final | 10/3/2023 | Approved | SCOTT FINNILA |
| METHANE-Final | 10/3/2023 | Not Ready for Inspection | SCOTT FINNILA |
| METHANE-Rough | 10/3/2023 | Approved | SCOTT FINNILA |
| METHANE-Subgrade | 10/3/2023 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 10/3/2023 | SGSOV Not Ready | SCOTT FINNILA |
| Smoke Detectors | 10/3/2023 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 10/10/2023 | Approved | SCOTT FINNILA |
| Final | 10/10/2023 | OK to Issue CofO | SCOTT FINNILA |
| HVAC-Final | 10/10/2023 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 10/10/2023 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 10/10/2023 | SGSOV Approved | SCOTT FINNILA |