2864 N PACIFIC VIEW TR 90068
Certificate Information: 2864 N PACIFIC VIEW TR 90068
- Application / Permit
- 21014-10000-02206
- Plan Check / Job No.
- B21LA08346
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED INTERIOR REMODEL TO EXISTING SFD, SCOPE WILL INCLUDE A PATIO ENCLOSURE AND TWO NEW UNCOVERED BALCONIES AT REAR.
- Permit Issued
- Issued on 8/19/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/18/2022
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2021 | MICHAEL LOPEZ |
| Corrections Issued | 6/3/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 6/9/2021 | WING SUEN |
| Building Plans Picked Up | 6/14/2021 | APPLICANT |
| Applicant returned to address corrections | 7/22/2021 | CARLOS MONTES |
| Plan Check Approved | 8/19/2021 | MICHAEL LOPEZ |
| Issued | 8/19/2021 | APPLICANT |
| Permit Finaled | 4/15/2022 | BRIAN SULLIVAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 6/15/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/15/2021 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 6/21/2021 | BRIAN MILLER |
| Miscellaneous | Cleared | 6/30/2021 | OLGA AYALA |
| Specific Plan | Cleared | 6/30/2021 | OLGA AYALA |
Contact Information
| Contractor | Golden Age Builders; Lic. No.: 1040171-B | 8265 SUNSET BLVD UNIT 205 WEST HOLLYWOOD, CA 90046 |
| Engineer | Manesh,, Behnam Abraham; Lic. No.: C38454 | 17337 VENTURA BLVD STE 112 ENCINO, CA 91316 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/1/2021 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2021 | Partial Approval | RUBEN SALAS |
| HVAC-Rough | 10/15/2021 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 10/15/2021 | Approved | COREY HUPP |
| HVAC-Rough | 10/22/2021 | Conditional Approval | SCOTT FINNILA |
| Shower Pan | 10/22/2021 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 10/28/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 10/28/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 11/3/2021 | Conditional Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 11/3/2021 | Partial Approval | BRIAN SULLIVAN |
| Insulation | 12/28/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 12/28/2021 | Approved | RAUL BARAJAS |
| Drywall Nailing | 1/4/2022 | Approved | BRIAN SULLIVAN |
| Final | 4/15/2022 | Permit Finaled | BRIAN SULLIVAN |
| Green Building Final | 4/15/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/15/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 4/15/2022 | Approved | BRIAN SULLIVAN |