1319 W LAS FLORES DR 90041
Certificate Information: 1319 W LAS FLORES DR 90041
- Application / Permit
- 21014-10000-02202
- Plan Check / Job No.
- B21LA08329
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION (2-STORY) AND REMODEL TO (E) SFD (1-STORY)
- Permit Issued
- Issued on 9/30/2021
- Issuing Office
- Current Status
- CofO Issued on 4/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | CARLOS MONTES |
| Corrections Issued | 5/25/2021 | CARLOS MONTES |
| Quality Review Completed | 6/1/2021 | KEN GILL |
| Building Plans Picked Up | 6/4/2021 | APPLICANT |
| Applicant returned to address corrections | 7/8/2021 | CARLOS MONTES |
| Plan Check Approved | 9/14/2021 | CARLOS MONTES |
| Plan Check Approved | 9/16/2021 | CARLOS MONTES |
| Issued | 9/30/2021 | APPLICANT |
| CofO in Progress | 4/7/2022 | CRAIG VAUGHAN |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
| CofO Issued | 4/13/2022 | DEROLD HAUFF |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 6/3/2021 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 6/3/2021 | CARLOS MONTES |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 6/10/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 8/8/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 8/12/2021 | THAN WIN |
| Hydrant and Access approval | Cleared | 8/18/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | George,, George Amgad; Lic. No.: C91528 | 5 BROWNFIELD LN POMONA, CA 91766 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/19/2021 | Partial Inspection | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 10/28/2021 | No Access for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 10/29/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 10/29/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 11/1/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Pre-Inspection | 11/9/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/18/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2021 | Not Ready for Inspection | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 1/18/2022 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 1/25/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 1/26/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 1/28/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 1/28/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 1/28/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 1/28/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 1/31/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/4/2022 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 2/7/2022 | Approved | CHARLES BOGHOSKHAN |
| Gas Test | 2/7/2022 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Green Building Rough | 2/7/2022 | Approved | CHARLES BOGHOSKHAN |
| Underground Mechanical | 2/8/2022 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 2/25/2022 | Corrections Issued | CRAIG VAUGHAN |
| Underground Mechanical | 3/1/2022 | Approved | CHARLES BOGHOSKHAN |
| Underground Mechanical | 3/10/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/16/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 3/16/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/21/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 3/21/2022 | Approved | CRAIG VAUGHAN |
| Gas Test | 3/24/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 3/31/2022 | No Access for Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 4/4/2022 | Approved | CRAIG VAUGHAN |
| Final | 4/4/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/4/2022 | Approved | CRAIG VAUGHAN |
| Green Building Final | 4/4/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 4/4/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/6/2022 | Approved | CRAIG VAUGHAN |
| Final | 4/6/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 4/6/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 4/6/2022 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/6/2022 | Approved | CRAIG VAUGHAN |