1319 W LAS FLORES DR 90041

Certificate Information: 1319 W LAS FLORES DR 90041

Application / Permit
21014-10000-02202
Plan Check / Job No.
B21LA08329
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
GROUND FLOOR ADDITION (2-STORY) AND REMODEL TO (E) SFD (1-STORY)
Permit Issued
Issued on 9/30/2021
Issuing Office
Current Status
CofO Issued on 4/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 CARLOS MONTES
Corrections Issued 5/25/2021 CARLOS MONTES
Quality Review Completed 6/1/2021 KEN GILL
Building Plans Picked Up 6/4/2021 APPLICANT
Applicant returned to address corrections 7/8/2021 CARLOS MONTES
Plan Check Approved 9/14/2021 CARLOS MONTES
Plan Check Approved 9/16/2021 CARLOS MONTES
Issued 9/30/2021 APPLICANT
CofO in Progress 4/7/2022 CRAIG VAUGHAN
Permit Finaled 4/13/2022 DEROLD HAUFF
CofO Issued 4/13/2022 DEROLD HAUFF
Permit Finaled 4/13/2022 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 6/3/2021 CARLOS MONTES
Grading Pre-Inspection Cleared 6/3/2021 CARLOS MONTES
Eng Process Fee Ord 176,300 Cleared 6/10/2021 RENZ SORIANO
Sewer availability Cleared 6/10/2021 RENZ SORIANO
Low Impact Development Cleared 8/8/2021 TA ANH
Roof/Waste drainage to street Cleared 8/12/2021 THAN WIN
Hydrant and Access approval Cleared 8/18/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer George,, George Amgad; Lic. No.: C91528 5 BROWNFIELD LN      POMONA, CA 91766

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/19/2021 Partial Inspection CRAIG VAUGHAN
Deputy Drilled-In Anchors 10/28/2021 No Access for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 10/29/2021 Not Ready for Inspection BRIAN SULLIVAN
Underground Mechanical 10/29/2021 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 11/1/2021 Conditional Approval HAMIK HARTOUNIAN
Pre-Inspection 11/9/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 11/18/2021 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 11/30/2021 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Not Ready for Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 1/3/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/4/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/10/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 1/18/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 1/25/2022 Approved CRAIG VAUGHAN
Insulation 1/26/2022 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 1/28/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 1/28/2022 Approved CRAIG VAUGHAN
Green Building Rough 1/28/2022 Approved CRAIG VAUGHAN
HVAC-Rough 1/28/2022 Approved CRAIG VAUGHAN
Insulation 1/31/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 2/4/2022 Approved CHARLES BOGHOSKHAN
Drywall Nailing 2/7/2022 Approved CHARLES BOGHOSKHAN
Gas Test 2/7/2022 Not Ready for Inspection CHARLES BOGHOSKHAN
Green Building Rough 2/7/2022 Approved CHARLES BOGHOSKHAN
Underground Mechanical 2/8/2022 Partial Approval CRAIG VAUGHAN
Underground Mechanical 2/25/2022 Corrections Issued CRAIG VAUGHAN
Underground Mechanical 3/1/2022 Approved CHARLES BOGHOSKHAN
Underground Mechanical 3/10/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 3/16/2022 Not Ready for Inspection CRAIG VAUGHAN
Service/Power Release 3/16/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 3/21/2022 Not Ready for Inspection CRAIG VAUGHAN
Service/Power Release 3/21/2022 Approved CRAIG VAUGHAN
Gas Test 3/24/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 3/31/2022 No Access for Inspection SCOTT FINNILA
BUILDING-Rough-Frame 4/4/2022 Approved CRAIG VAUGHAN
Final 4/4/2022 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 4/4/2022 Approved CRAIG VAUGHAN
Green Building Final 4/4/2022 Approved CRAIG VAUGHAN
HVAC-Final 4/4/2022 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/4/2022 SGSOV Approved CRAIG VAUGHAN
ELECTRICAL-Final 4/6/2022 Approved CRAIG VAUGHAN
Final 4/6/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 4/6/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 4/6/2022 Approved CRAIG VAUGHAN
Smoke Detectors 4/6/2022 Approved CRAIG VAUGHAN