12923 W DEWEY ST 90066
Certificate Information: 12923 W DEWEY ST 90066
- Application / Permit
- 21014-10000-02201
- Plan Check / Job No.
- B21LA08328
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE AND ADDITION TO (N) ADU
- Permit Issued
- Issued on 3/14/2022
- Issuing Office
- Current Status
- CofO Issued on 12/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2021 | RICARDO RAMIREZ |
| Corrections Issued | 5/7/2021 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 10/20/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 1/19/2022 | RAHEL BEYENE |
| Plan Check Approved | 3/10/2022 | FERNANDO FLORES |
| Issued | 3/14/2022 | APPLICANT |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| CofO in Progress | 12/19/2022 | RICHARD STEINBACH |
| Permit Finaled | 12/21/2022 | DANIEL ORRANTE |
| CofO Issued | 12/21/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/21/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/18/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2021 | DINAH GARIN |
| Sewer availability | Cleared | 5/20/2021 | DINAH GARIN |
| Construction near power lines | Cleared | 8/4/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 11/2/2021 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 2/14/2022 | TRACY TATE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/20/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/22/2022 | Corrections Issued | PATRICK QUALEY |
| PLUMBING-Rough | 7/25/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/27/2022 | Partial Approval | STEPHANIE SWANSON |
| Sewer | 7/27/2022 | Approved | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 8/4/2022 | No Access for Inspection | KENNETH NAGLE |
| Deputy Other (see comments) | 8/4/2022 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 8/4/2022 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/19/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 9/19/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/19/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 9/23/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/11/2022 | Approved | CLAYTON GRAHAM |
| Shower Pan | 10/11/2022 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 10/17/2022 | Conditional Approval | HERBERT GIRON |
| Green Building Rough | 10/17/2022 | Conditional Approval | HERBERT GIRON |
| Insulation | 10/17/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 10/17/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/21/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 10/21/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 10/21/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/2/2022 | Corrections Issued | JUAN VALENZUELA |
| Final | 12/2/2022 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 12/2/2022 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 12/2/2022 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Final | 12/2/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 12/2/2022 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Not Ready | JUAN VALENZUELA |
| Smoke Detectors | 12/2/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 12/9/2022 | Approved | JESUS RODRIGUEZ |
| Final | 12/9/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 12/9/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Final | 12/9/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 12/9/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 12/9/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/14/2022 | Approved | JESUS RODRIGUEZ |
| Final | 12/14/2022 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Final | 12/14/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 12/14/2022 | Approved | JESUS RODRIGUEZ |