3935 W AVENUE 43 90041
Certificate Information: 3935 W AVENUE 43 90041
- Application / Permit
- 21014-10000-02194
- Plan Check / Job No.
- B21LA08288
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2ND STORY ADDITION TO (E) SINGLE FAMILY DWELLING. INTERIOR REMODEL.
- Permit Issued
- Issued on 5/31/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2021 | KEVIN MORALES |
| Corrections Issued | 5/20/2021 | KEVIN MORALES |
| Quality Review Completed | 5/25/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 2/8/2022 | KEVIN MORALES |
| Plan Check Approved | 4/13/2022 | KEVIN MORALES |
| Building Plans Picked Up | 4/22/2022 | APPLICANT |
| Issued | 5/31/2022 | APPLICANT |
| CofO in Progress | 8/3/2023 | CRAIG VAUGHAN |
| CofO Issued | 8/7/2023 | RONALD MYRICK |
| Permit Finaled | 8/7/2023 | RONALD MYRICK |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/23/2021 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 11/23/2021 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 11/23/2021 | JEANIE LAM |
| Sewer availability | Cleared | 11/23/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 1/19/2022 | ANTHONY VARGAS |
| BHO/Hillside ordinance | Cleared | 1/26/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 1/28/2022 | JEANIE LAM |
| GPI Written Notices | Cleared | 1/31/2022 | KEVIN MORALES |
| Grading Pre-Inspection | Cleared | 1/31/2022 | KEVIN MORALES |
| Distance to fire station | Cleared | 2/12/2022 | RUEL COLE |
| Hydrant and Access approval | Cleared | 2/12/2022 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khanlou,, Amir; Lic. No.: C87550 | 10671 HOLMAN AVE APT 207 LOS ANGELES, CA 90024 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/20/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Deputy Drilled-In Anchors | 8/1/2022 | Conditional Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/4/2022 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/8/2022 | Partial Approval | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 8/18/2022 | Conditional Approval | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 8/19/2022 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/19/2022 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/19/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deputy Wood Construction | 9/22/2022 | Conditional Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/18/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 10/27/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 11/15/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 11/15/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/15/2022 | Approved | CRAIG VAUGHAN |
| Wood Frame | 11/15/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/18/2022 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 11/18/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 11/18/2022 | Approved | BRIAN SULLIVAN |
| Wood Frame | 11/18/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Approval | OSVALDO PARAMO |
| Shower Pan | 12/6/2022 | Approved | OSVALDO PARAMO |
| Wood Frame | 12/6/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/27/2022 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 12/27/2022 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 12/29/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 12/29/2022 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 12/30/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 1/12/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 1/17/2023 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 1/24/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 1/24/2023 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 1/27/2023 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 4/11/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/11/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 4/11/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/11/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 4/11/2023 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/11/2023 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/11/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/13/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 4/13/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 4/13/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 4/19/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Final | 4/19/2023 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Not Ready | BRIAN SULLIVAN |
| ELECTRICAL-Final | 6/12/2023 | Approved | OSVALDO PARAMO |
| Final | 6/12/2023 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Final | 6/12/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 6/12/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Approved | OSVALDO PARAMO |
| Final | 8/2/2023 | OK to Issue CofO | CRAIG VAUGHAN |