1947 N VAN NESS AVE 90068

Certificate Information: 1947 N VAN NESS AVE 90068

Application / Permit
21014-10000-02167
Plan Check / Job No.
B21LA08208
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. CONVERT EXISTING RECREATION ROOM INTO AN ADU WITH NEW ADDITION PER ORDINANCE.
Permit Issued
Issued on 2/1/2023
Issuing Office
Current Status
CofO Issued on 4/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 MICHAEL LOPEZ
Corrections Issued 6/28/2021 MICHAEL LOPEZ
Quality Review Completed 7/6/2021 WING SUEN
Applicant returned to address corrections 6/2/2022 MICHAEL LOPEZ
Plan Check Approved 12/23/2022 MAHNAZ NOURHASHEMI
Issued 2/1/2023 APPLICANT
CofO in Progress 4/22/2026 CRAIG VAUGHAN
CofO Issued 4/23/2026 DEROLD HAUFF
Permit Finaled 4/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/2/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/7/2022 CARLOS AGUILERA
Sewer availability Cleared 4/7/2022 CARLOS AGUILERA
HPOZ Cleared 5/31/2022 DEEPEAKA DHALIWAL
Low Impact Development Cleared 9/30/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 10/3/2022 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 10/14/2022 MANUEL TEJADA

Contact Information

Contractor Grid Line Structures Inc; Lic. No.: 1070999-B       ,
Engineer Torres,, Efren Santos; Lic. No.: S2340 16003 S INDIAN CREEK RD      CERRITOS, CA 90701

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/4/2023 Partial Inspection STUART CHAPMAN
PLUMBING-Rough 7/24/2024 Not Ready for Inspection ROY SPAULDING
Underground Mechanical 7/24/2024 Partial Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 8/2/2024 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 8/2/2024 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/16/2024 Approved ROY SPAULDING
Footing/Foundation/Slab 8/16/2024 Approved ROY SPAULDING
PLUMBING-Rough 8/20/2024 Not Ready for Inspection ROY SPAULDING
Underground Mechanical 8/20/2024 Approved ROY SPAULDING
Underground Mechanical 11/7/2024 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 1/16/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 1/16/2025 Corrections Issued BRENDAN MORELLI
HVAC-Rough 1/17/2025 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 2/6/2025 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 2/6/2025 Approved CRAIG VAUGHAN
HVAC-Rough 2/6/2025 Approved CRAIG VAUGHAN
PLUMBING-Rough 2/6/2025 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Partial Approval CRAIG VAUGHAN
Underground Mechanical 2/26/2025 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 3/11/2025 Partial Approval CRAIG VAUGHAN
Insulation 4/9/2025 Approved CRAIG VAUGHAN
Shower Pan 4/9/2025 Approved CRAIG VAUGHAN
Drywall Nailing 4/17/2025 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 5/8/2025 Approved CRAIG VAUGHAN
Special/Order Compliance 8/18/2025 Partial Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 9/17/2025 No Access for Inspection BRIAN SULLIVAN
Final 9/17/2025 No Access for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/17/2025 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 9/17/2025 No Access for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 9/22/2025 Partial Approval CRAIG VAUGHAN
Final 9/22/2025 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/22/2025 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 9/22/2025 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 10/10/2025 Approved CRAIG VAUGHAN
Final 10/10/2025 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV Not Ready CRAIG VAUGHAN
Final 4/21/2026 OK to Issue CofO CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/21/2026 SGSOV Approved CRAIG VAUGHAN