1436 W 54TH ST 90062

Certificate Information: 1436 W 54TH ST 90062

Application / Permit
21014-10000-02155
Plan Check / Job No.
B21LA08168
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 1 story bedroom addition ( 15'-3" x 13'-11") to existing 1 story SFD.
Permit Issued
Issued on 11/4/2021
Issuing Office
Current Status
Issued on 11/4/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/29/2021 APPLICANT
Assigned to Plan Check Engineer 4/30/2021 RAMA DABADGE
Corrections Issued 5/3/2021 RAMA DABADGE
Plan Check Approved 8/13/2021 ADAM HEGAZI
Issued 11/4/2021 APPLICANT
Building Plans Picked Up 11/4/2021 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/8/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 6/11/2021 THOMAS LANG
Sewer availability Cleared 6/11/2021 THOMAS LANG
Community Plan Implem. Overlay Cleared 7/20/2021 RAFAEL FONTES

Contact Information

Contractor Bell Construction West; Lic. No.: 853579-B P O BOX 2398      RIALTO, CA 92377

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/17/2021 Approved SABAS ALONSO
Special/Order Compliance 11/24/2021 Approved SABAS ALONSO
Deputy Drilled-In Anchors 12/6/2021 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 12/16/2021 Approved STUART CHAPMAN
Special/Order Compliance 2/3/2022 Approved HORACE FULTZ
BUILDING-Rough-Frame 3/31/2022 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Corrections Issued SABAS ALONSO
Green Building Rough 3/31/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 5/20/2022 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/20/2022 Approved SABAS ALONSO
Green Building Rough 5/20/2022 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 5/27/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 5/27/2022 Approved SABAS ALONSO
Green Building Rough 5/27/2022 Approved SABAS ALONSO
HVAC-Rough 5/27/2022 Approved SABAS ALONSO
Drywall Nailing 11/2/2022 No Access for Inspection MICHAEL LEWIS
Green Building Final 11/2/2022 No Access for Inspection MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 11/2/2022 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 11/2/2022 No Access for Inspection MICHAEL LEWIS
Drywall Nailing 11/3/2022 Approved SABAS ALONSO
Insulation 11/3/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 11/3/2022 Approved SABAS ALONSO
Final 11/10/2022 Not Ready for Inspection SABAS ALONSO
Final 6/13/2023 No Access for Inspection SABAS ALONSO
Green Building Final 6/13/2023 No Access for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/13/2023 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 6/13/2023 No Access for Inspection SABAS ALONSO
Final 6/26/2023 Corrections Issued SABAS ALONSO
Green Building Final 6/26/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/26/2023 SGSOV Approved SABAS ALONSO
Smoke Detectors 6/26/2023 Approved SABAS ALONSO
Final 1/30/2024 Not Ready for Inspection RONNIE MINDANAO