2805 E BOULDER ST 90033

Certificate Information: 2805 E BOULDER ST 90033

Application / Permit
21014-10000-02139
Plan Check / Job No.
B21LA08100
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO GARAGE AND CONVERT TO ADU.
Permit Issued
Issued on 6/2/2022
Issuing Office
Current Status
CofO Issued on 6/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2021 APPLICANT
Assigned to Plan Check Engineer 5/10/2021 JOE VO
Corrections Issued 5/10/2021 JOE VO
Applicant returned to address corrections 6/10/2021 JOE VO
Plan Check Approved 11/6/2021 JOE VO
Issued 6/2/2022 APPLICANT
CofO in Progress 5/30/2023 OSVALDO PARAMO
CofO in Progress 5/30/2023 OSVALDO PARAMO
CofO Issued 6/8/2023 DEROLD HAUFF
Permit Finaled 6/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/4/2021 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 6/4/2021 JEREMY CHOK
Roof/Waste drainage to street Cleared 6/4/2021 JEREMY CHOK
Construction near power lines Cleared 11/2/2021 RIDWAN HARDY
Sewer availability Cleared 6/1/2022 JEREMY CHOK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/7/2022 Approved OSVALDO PARAMO
Footing/Foundation/Slab 7/14/2022 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 8/19/2022 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 8/23/2022 Approved OSVALDO PARAMO
Footing/Foundation/Slab 8/23/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 10/20/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 11/7/2022 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 11/16/2022 Approved OSVALDO PARAMO
HVAC-Rough 11/16/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 11/16/2022 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 11/29/2022 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 11/29/2022 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 12/6/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 12/12/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/19/2022 Conditional Approval OSVALDO PARAMO
Interior/Exterior Lathing 12/19/2022 Partial Approval OSVALDO PARAMO
Insulation 12/23/2022 Approved OSVALDO PARAMO
Drywall Nailing 12/30/2022 Approved RUBEN SALAS
Interior/Exterior Lathing 2/15/2023 Approved OSVALDO PARAMO
Shower Pan 2/15/2023 Approved OSVALDO PARAMO
Service/Power Release 2/28/2023 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 3/9/2023 Approved OSVALDO PARAMO
Final 3/9/2023 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 3/9/2023 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 3/9/2023 Approved OSVALDO PARAMO
Final 4/4/2023 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 4/4/2023 SGSOV Not Ready OSVALDO PARAMO
Service/Power Release 4/4/2023 Approved OSVALDO PARAMO
Final 5/1/2023 Conditional Approval OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/1/2023 SGSOV Approved OSVALDO PARAMO
Final 5/24/2023 OK to Issue CofO OSVALDO PARAMO