9641 W ROYALTON DR 90210
Certificate Information: 9641 W ROYALTON DR 90210
- Application / Permit
- 21014-10000-02135
- Plan Check / Job No.
- B21LA08083
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- RENOVATION AND ADDITIONTO AN EXISTINGTWO-STORY SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED GARAGE
- Permit Issued
- Issued on 11/4/2021
- Issuing Office
- Current Status
- Issued on 5/15/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | VU NGUYEN |
| Corrections Issued | 5/18/2021 | VU NGUYEN |
| Quality Review Completed | 5/19/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 5/21/2021 | APPLICANT |
| Applicant returned to address corrections | 6/17/2021 | VU NGUYEN |
| Applicant returned to address corrections | 8/14/2021 | VU NGUYEN |
| Plan Check Approved | 11/4/2021 | VU NGUYEN |
| Issued | 11/4/2021 | APPLICANT |
| CofO in Progress | 5/5/2023 | RAUL BARAJAS |
| No Progress | 5/15/2023 | RAUL BARAJAS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/2/2021 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 6/2/2021 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 6/2/2021 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 6/2/2021 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 6/2/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 6/8/2021 | ANTHONY MAINEZ |
| Miscellaneous | Cleared | 6/9/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 6/9/2021 | DENZEL HENDERSON |
| Low Impact Development | Cleared | 9/21/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 10/1/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 11/4/2021 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 11/4/2021 | VU NGUYEN |
Contact Information
| Architect | Feldman,, Jonathan H; Lic. No.: C28459 | 1648 B PACIFIC AVENUE SAN FRANCISCO, CA 94109 |
| Contractor | Klein Construction; Lic. No.: 891079-B | 13858 CHANDLER BLVD SHERMAN OAKS, CA 91401 |
| Engineer | Kwan,, Denny Chi-Ho; Lic. No.: S4887 | 5638 NEWFIELDS LN DUBLIN, CA 94568 |
| Geologist | Daugherty,, Daniel Thomas; Lic. No.: EG2569 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/1/2021 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Approved | RAUL BARAJAS |
| Deputy Wood Construction | 3/11/2022 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/24/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Pre-Inspection | 5/10/2022 | Partial Inspection | RAUL BARAJAS |
| Gas Test | 6/6/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/6/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Sewer | 6/6/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/22/2022 | Approved | RAUL BARAJAS |
| HVAC-Rough | 6/30/2022 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 7/14/2022 | Partial Approval | RAUL BARAJAS |
| HVAC-Rough | 7/14/2022 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 7/20/2022 | Approved | RAUL BARAJAS |
| HVAC-Rough | 7/20/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 7/20/2022 | Approved | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 7/27/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 7/27/2022 | Conditional Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/28/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Approved | RAUL BARAJAS |
| Insulation | 8/2/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 8/9/2022 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 8/10/2022 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 8/15/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 8/15/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 12/21/2022 | Approved | RAUL BARAJAS |
| Pre-Inspection | 2/13/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/24/2023 | Approved | STUART CHAPMAN |
| Final | 4/24/2023 | Conditional Approval | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/24/2023 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 4/24/2023 | Approved | STUART CHAPMAN |
| Final | 5/5/2023 | OK to Issue CofO | RAUL BARAJAS |