1815 N BEL-AIR ROAD 90077

Certificate Information: 1815 N BEL-AIR ROAD 90077

Application / Permit
21014-10000-02126
Plan Check / Job No.
B21LA08066
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND ALTERATION TO (E) 3-STORY SINGLE FAMILY DWELLING: -RE-ROOFING OF EXISTING ROOF AND EXISTING BALCONIES -REPLACE AND ENLARAGE (E) WINDOWS -REPLACEMENT OF (E) METAL STAIR WITH NEW STAIR -RECONFIGURATION OF (E) STEPS, POND, WALLS AND PAVING AT FRONT ENTRANCE -ADDITION
Permit Issued
Issued on 8/9/2021
Issuing Office
Current Status
CofO Issued on 12/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 DANIEL YIP
Corrections Issued 5/18/2021 DANIEL YIP
Quality Review Completed 5/25/2021 KEN GILL
Building Plans Picked Up 5/27/2021 APPLICANT
Applicant returned to address corrections 7/1/2021 DANIEL YIP
Plan Check Approved 8/9/2021 DANIEL YIP
Issued 8/9/2021 APPLICANT
CofO in Progress 12/6/2022 CHRISTOPHER WILSON
CofO in Progress 12/6/2022 CHRISTOPHER WILSON
Permit Finaled 12/13/2022 DANIEL ORRANTE
CofO Issued 12/13/2022 DANIEL ORRANTE
Permit Finaled 12/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/1/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 7/6/2021 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 7/28/2021 DANIEL YIP

Contact Information

Architect Mckelvey,, Stephen Fred; Lic. No.: C33135 2854 E LARKHILL DRIVE      WEST COVINA, CA 91791
Contractor Owner-Builder       ,
Engineer Behshid,, Farshid; Lic. No.: S4585 4647 ENCINAS DR      LA CANADA, CA 91011

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/26/2021 Corrections Issued CHRISTOPHER WILSON
Sewer 8/26/2021 Approved CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/27/2021 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/27/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/8/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 10/13/2021 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 10/27/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 10/27/2021 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 11/2/2021 Approved CHRISTOPHER WILSON
Footing/Foundation/Slab 11/19/2021 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/16/2021 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 12/16/2021 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 12/16/2021 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 12/16/2021 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Not Ready for Inspection CHRISTOPHER WILSON
Special/Order Compliance 12/20/2021 Partial Inspection CLAYTON GRAHAM
ELECTRICAL-Rough 12/29/2021 Approved BRENDAN LOONEY
Wood Frame 12/29/2021 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 1/28/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Rough 1/28/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 2/17/2022 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 2/18/2022 Partial Approval CHRISTOPHER WILSON
Insulation 2/24/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 2/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
Shower Pan 2/25/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 3/1/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 3/4/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 3/4/2022 Approved CHRISTOPHER WILSON
Insulation 3/4/2022 Approved CHRISTOPHER WILSON
Drywall Nailing 3/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 3/8/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 3/9/2022 Approved CHRISTOPHER WILSON
Drywall Nailing 3/11/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Final 8/30/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 8/31/2022 Approved CHRISTOPHER WILSON
PLUMBING-Final 9/6/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Final 9/9/2022 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 9/22/2022 Approved CHRISTOPHER WILSON
PLUMBING-Final 9/22/2022 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 11/7/2022 Approved CHRISTOPHER WILSON
Drywall Nailing 11/7/2022 Approved CHRISTOPHER WILSON
Final 11/7/2022 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 11/7/2022 Approved CHRISTOPHER WILSON
Green Building Final 11/7/2022 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 11/7/2022 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 11/7/2022 Approved CHRISTOPHER WILSON
Final 12/5/2022 OK to Issue CofO CHRISTOPHER WILSON