11955 W WOODBINE ST 90066

Certificate Information: 11955 W WOODBINE ST 90066

Application / Permit
21014-10000-02122
Plan Check / Job No.
B21LA08059
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION/REMODEL OF SFD/GARAGE: ADD TWO BEDROOMS AND BATHROOM. CONVERT TWO [E] BEDROOMS TO: STUDY, CLOSET, LAUNDRY CLOSET, AND ENLARGE [E] BATHROOM.
Permit Issued
Issued on 4/20/2022
Issuing Office
Current Status
CofO Issued on 12/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2021 APPLICANT
Assigned to Plan Check Engineer 6/9/2021 SINA KHOSRAVI
Corrections Issued 6/9/2021 SINA KHOSRAVI
Applicant returned to address corrections 7/23/2021 STARR CHEN
Applicant returned to address corrections 8/16/2021 DANIEL SANJUAN
Applicant returned to address corrections 9/17/2021 JOSEPH RAFOLS
Plan Check Approved 12/1/2021 JESSE JIMENEZ
Building Plans Picked Up 12/3/2021 APPLICANT
Issued 4/20/2022 APPLICANT
CofO in Progress 7/5/2023 JEREMY TODD
Permit Finaled 12/30/2023 DANIEL ORRANTE
CofO Issued 12/30/2023 DANIEL ORRANTE
Permit Finaled 12/30/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 6/24/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/25/2021 DINAH GARIN
Grading Pre-Inspection Cleared 6/28/2021 BRIAN MILLER
Low Impact Development Cleared 11/2/2021 KHAING AYE
Roof/Waste drainage to street Cleared 11/18/2021 TRACY TATE

Contact Information

Contractor Karma Remodel & Development Inc; Lic. No.: 875130-B 21610 VENTURA BLVD      WOODLAND HILLS, CA 91364
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/15/2022 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 6/17/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Partial Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Partial Approval JOHNNY MIRANDA
Sewer 6/30/2022 Approved JOHNNY MIRANDA
Deputy Drilled-In Anchors 7/20/2022 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 7/25/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 8/15/2022 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 8/15/2022 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 8/15/2022 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 8/19/2022 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 8/19/2022 Partial Approval JOHNNY MIRANDA
Green Building Rough 8/19/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 8/19/2022 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 8/19/2022 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 8/26/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 8/26/2022 Approved JOHNNY MIRANDA
Green Building Rough 8/26/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 8/26/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 8/26/2022 Approved JOHNNY MIRANDA
Insulation 8/31/2022 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 8/31/2022 Not Ready for Inspection JOHNNY MIRANDA
Shower Pan 8/31/2022 Corrections Issued JOHNNY MIRANDA
Interior/Exterior Lathing 9/7/2022 Partial Approval JOHNNY MIRANDA
Shower Pan 9/7/2022 Not Ready for Inspection JOHNNY MIRANDA
Green Building Rough 9/14/2022 Not Ready for Inspection JOHNNY MIRANDA
Shower Pan 9/14/2022 Approved JOHNNY MIRANDA
Drywall Nailing 10/18/2022 Approved JOHNNY MIRANDA
Green Building Rough 10/18/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 10/18/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 4/11/2023 Approved JOHNNY MIRANDA
Final 4/11/2023 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 4/11/2023 Approved JOHNNY MIRANDA
Green Building Final 4/11/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 4/11/2023 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 4/11/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Final 7/3/2023 Approved JEREMY TODD
Final 7/3/2023 OK to Issue CofO JEREMY TODD