2723 W COLISEUM ST 90018
Certificate Information: 2723 W COLISEUM ST 90018
- Application / Permit
- 21014-10000-02107
- Plan Check / Job No.
- B21LA08002
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1-STORY GARAGE CONVERSION TO ADU AND ADDITION 73 SF ADDITION PER CA GC 65852.2(e)(1)(B) AND LAMC 12.22A.33(c)-(d), (g). 2 OF 2
- Permit Issued
- Issued on 9/19/2022
- Issuing Office
- Current Status
- Issued on 9/19/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | VIVIAN LAO |
| Corrections Issued | 6/10/2021 | VIVIAN LAO |
| Quality Review Completed | 6/17/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 6/29/2021 | APPLICANT |
| Applicant returned to address corrections | 3/7/2022 | VIVIAN LAO |
| Plan Check Approved | 5/4/2022 | VIVIAN LAO |
| Plan Check Approved | 9/19/2022 | ALLEN MANALANSAN |
| Issued | 9/19/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/20/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/20/2021 | JEANIE LAM |
| Construction near power lines | Cleared | 11/17/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2021 | JEANIE LAM |
| Sewer availability | Cleared | 11/17/2021 | JEANIE LAM |
Contact Information
| Contractor | Cp3 Construction Inc; Lic. No.: 1095066-B | 10557 JEFFERSON BLVD SUITE D CULVER CITY, CA 90016 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/21/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 10/21/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/25/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 10/25/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 11/4/2022 | Partial Approval | ANTHONY EGSON |
| Wood Frame | 11/10/2022 | No Access for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 4/21/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Shower Pan | 4/21/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 4/26/2023 | Corrections Issued | ANTHONY EGSON |
| Shower Pan | 4/26/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 5/30/2023 | Approved | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 6/1/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/29/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/5/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Drywall Nailing | 9/5/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 9/5/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 9/5/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 9/5/2024 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/5/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 9/5/2024 | Approved | ANTHONY EGSON |