2725 W COLISEUM ST 90018
Certificate Information: 2725 W COLISEUM ST 90018
- Application / Permit
- 21014-10000-02105
- Plan Check / Job No.
- B21LA08002
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR (185 SF), SECOND STORY (808 SF), AND ATTACHED GARAGE (165 SF) ADDITION TO EXISTING 1-STORY SFD.
- Permit Issued
- Issued on 9/19/2022
- Issuing Office
- Current Status
- Issued on 9/19/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | VIVIAN LAO |
| Corrections Issued | 6/10/2021 | VIVIAN LAO |
| Quality Review Completed | 6/17/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 6/29/2021 | APPLICANT |
| Applicant returned to address corrections | 3/7/2022 | VIVIAN LAO |
| Plan Check Approved | 5/4/2022 | VIVIAN LAO |
| Issued | 9/19/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2021 | JEANIE LAM |
| Sewer availability | Cleared | 11/17/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 1/24/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/25/2022 | JEANIE LAM |
| Trees in Parkway | Cleared | 2/1/2022 | ADALBERTO VERA |
| Permit | Cleared | 2/25/2022 | JEANIE LAM |
Contact Information
| Contractor | Cp3 Construction Inc; Lic. No.: 1095066-B | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/19/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/19/2022 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/22/2022 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Partial Approval | ANTHONY EGSON |
| Wood Frame | 11/22/2022 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 12/23/2022 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 12/30/2022 | Corrections Issued | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 5/1/2023 | No Access for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 5/30/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 6/1/2023 | Corrections Issued | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 6/1/2023 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 6/16/2023 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 6/20/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/29/2023 | Approved | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 6/29/2023 | Partial Approval | ANTHONY EGSON |
| Sewer | 10/23/2023 | Corrections Issued | ANTHONY EGSON |
| Sewer | 10/31/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/5/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Drywall Nailing | 9/5/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 9/5/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/5/2024 | Approved | ANTHONY EGSON |
| Green Building Final | 9/5/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 9/5/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/5/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 9/5/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Pre-Inspection | 3/11/2025 | Partial Approval | LUIS CASTRO |
| Pre-Inspection | 3/13/2025 | Partial Approval | LUIS CASTRO |
| Special/Order Compliance | 3/13/2025 | Partial Inspection | RAUL BARAJAS |