5222 N LOLETA AVE 90041
Certificate Information: 5222 N LOLETA AVE 90041
- Application / Permit
- 21014-10000-02061
- Plan Check / Job No.
- B21LA07789
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- DEMO OF (E) DILAPIDATED FRONT PORCH AND ROOF CONSTRUCTION OF NEW TIMBER POST AND BEAM FRONT PORCH, REPLACEMENT ROOF.
- Permit Issued
- Issued on 7/27/2021
- Issuing Office
- Current Status
- CofO Issued on 3/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 5/17/2021 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 6/15/2021 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 7/24/2021 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 7/27/2021 | FARSHAD ALIMOHAMADI |
| Issued | 7/27/2021 | APPLICANT |
| Building Plans Picked Up | 7/27/2021 | APPLICANT |
| CofO in Progress | 3/10/2023 | CRAIG VAUGHAN |
| CofO Issued | 3/15/2023 | DEROLD HAUFF |
| Permit Finaled | 3/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/23/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2021 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 7/22/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/21/2021 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 11/12/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 11/16/2021 | No Access for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 11/18/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Partial Approval | CRAIG VAUGHAN |
| Special/Order Compliance | 11/30/2021 | Partial Inspection | AMY COLIN |
| Deputy Wood Construction | 12/2/2021 | No Access for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/3/2021 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 12/3/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 12/3/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 12/14/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/9/2022 | Approved | CRAIG VAUGHAN |
| Final | 2/9/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/9/2022 | Approved | CRAIG VAUGHAN |
| Green Building Final | 2/9/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 2/9/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 2/9/2022 | Corrections Issued | CRAIG VAUGHAN |
| Final | 10/21/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 10/21/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 10/21/2022 | Approved | BRIAN SULLIVAN |
| Final | 11/4/2022 | Conditional Approval | CRAIG VAUGHAN |
| HVAC-Final | 11/4/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/9/2023 | Approved | CRAIG VAUGHAN |
| Final | 3/9/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| PLUMBING-Final | 3/9/2023 | Approved | CRAIG VAUGHAN |