Application / Permit
21014-10000-02051
Plan Check / Job No.
B21LA07708
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Proposed ground floor and second floor ADU addition to an existing detached garage per ordinance.
Permit Issued
Issued on 9/12/2022
Issuing Office
Current Status
CofO Issued on 4/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 MICHAEL LOPEZ
Corrections Issued 5/20/2021 MICHAEL LOPEZ
Quality Review Completed 5/27/2021 HERNAN ARREOLA
Applicant returned to address corrections 5/20/2022 MICHAEL LOPEZ
Applicant returned to address corrections 8/5/2022 MICHAEL LOPEZ
Plan Check Approved 8/11/2022 MICHAEL LOPEZ
Issued 9/12/2022 APPLICANT
CofO in Progress 4/12/2024 JOSE AVILA
Permit Finaled 4/23/2024 RUBEN SALAS
CofO Issued 4/23/2024 RUBEN SALAS
Permit Finaled 4/23/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/1/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/28/2021 CARLOS AGUILERA
Sewer availability Cleared 6/28/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 7/21/2021 MATTHEW CRAIG
Low Impact Development Cleared 6/10/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 6/16/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/4/2023 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 5/15/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Corrections Issued KIRK SANDERS
Green Building Rough 5/31/2023 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/2/2023 Partial Approval KIRK SANDERS
Special/Order Compliance 6/2/2023 Approved JUAN VALENZUELA
Deputy Wood Construction 6/23/2023 Conditional Approval MICHAEL SMITH
ELECTRICAL-Rough 7/24/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 7/24/2023 Corrections Issued KIRK SANDERS
Underground Mechanical 7/24/2023 Corrections Issued KIRK SANDERS
Wood Frame 7/24/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 7/31/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 7/31/2023 Approved KIRK SANDERS
Green Building Rough 7/31/2023 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 7/31/2023 Approved KIRK SANDERS
Underground Mechanical 7/31/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Approved JUAN VALENZUELA
Green Building Rough 8/8/2023 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 8/14/2023 Approved JUAN VALENZUELA
Green Building Rough 8/14/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 8/14/2023 Partial Approval JUAN VALENZUELA
Insulation 8/21/2023 Approved MISAEL ESPARZA
Drywall Nailing 8/24/2023 Approved MISAEL ESPARZA
Shower Pan 9/5/2023 Approved CHRISTOPHER ROJAS
Underground Mechanical 9/5/2023 Partial Approval CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/11/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 11/7/2023 Not Ready for Inspection JUAN VALENZUELA
Pre-Inspection 11/15/2023 Partial Inspection JUAN VALENZUELA
Final 2/8/2024 Corrections Issued JOSE AVILA
Green Building Final 2/8/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/8/2024 SGSOV Not Ready JOSE AVILA
Smoke Detectors 2/8/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 2/20/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 2/20/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 2/20/2024 Approved RAUL OLAGI
Final 4/11/2024 OK to Issue CofO JOSE AVILA
Service/Power Release 4/12/2024 Approved JOSE AVILA