5114 N FULTON AVE 91423
Certificate Information: 5114 N FULTON AVE 91423
- Application / Permit
- 21014-10000-02051
- Plan Check / Job No.
- B21LA07708
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Proposed ground floor and second floor ADU addition to an existing detached garage per ordinance.
- Permit Issued
- Issued on 9/12/2022
- Issuing Office
- Current Status
- CofO Issued on 4/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | MICHAEL LOPEZ |
| Corrections Issued | 5/20/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 5/27/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/20/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/5/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 8/11/2022 | MICHAEL LOPEZ |
| Issued | 9/12/2022 | APPLICANT |
| CofO in Progress | 4/12/2024 | JOSE AVILA |
| Permit Finaled | 4/23/2024 | RUBEN SALAS |
| CofO Issued | 4/23/2024 | RUBEN SALAS |
| Permit Finaled | 4/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/1/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/28/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 7/21/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/10/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 6/16/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/4/2023 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 5/15/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 5/31/2023 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Partial Approval | KIRK SANDERS |
| Special/Order Compliance | 6/2/2023 | Approved | JUAN VALENZUELA |
| Deputy Wood Construction | 6/23/2023 | Conditional Approval | MICHAEL SMITH |
| ELECTRICAL-Rough | 7/24/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 7/24/2023 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 7/24/2023 | Corrections Issued | KIRK SANDERS |
| Wood Frame | 7/24/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/31/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 7/31/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 7/31/2023 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 7/31/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 7/31/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Approved | JUAN VALENZUELA |
| Green Building Rough | 8/8/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/14/2023 | Approved | JUAN VALENZUELA |
| Green Building Rough | 8/14/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/14/2023 | Partial Approval | JUAN VALENZUELA |
| Insulation | 8/21/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 8/24/2023 | Approved | MISAEL ESPARZA |
| Shower Pan | 9/5/2023 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 9/5/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/11/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 11/7/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Pre-Inspection | 11/15/2023 | Partial Inspection | JUAN VALENZUELA |
| Final | 2/8/2024 | Corrections Issued | JOSE AVILA |
| Green Building Final | 2/8/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/8/2024 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 2/8/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 2/20/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/20/2024 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 2/20/2024 | Approved | RAUL OLAGI |
| Final | 4/11/2024 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 4/12/2024 | Approved | JOSE AVILA |