917 S 3RD AVE 90019
Certificate Information: 917 S 3RD AVE 90019
- Application / Permit
- 21014-10000-02050
- Plan Check / Job No.
- B21LA07694
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERSION OF (E) GARAGE & ADDITION FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c)&(d)
- Permit Issued
- Issued on 1/12/2022
- Issuing Office
- Current Status
- CofO Issued on 2/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | LAMAR DAVIS |
| Corrections Issued | 5/27/2021 | LAMAR DAVIS |
| Quality Review Completed | 6/6/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/4/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 12/1/2021 | LAMAR DAVIS |
| Plan Check Approved | 1/5/2022 | LAMAR DAVIS |
| Issued | 1/12/2022 | APPLICANT |
| Building Plans Picked Up | 6/30/2022 | APPLICANT |
| CofO in Progress | 2/23/2023 | ALIZAH MAYAGOITIA |
| CofO Issued | 2/24/2023 | DEROLD HAUFF |
| Permit Finaled | 2/24/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2021 | CECILIO NAVARRO |
| Address approval | Cleared | 6/29/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/2/2021 | CECILIO NAVARRO |
| HPOZ | Cleared | 10/14/2021 | AMANDA KAINER |
| ZI | Cleared | 10/14/2021 | AMANDA KAINER |
| Roof/Waste drainage to street | Cleared | 10/16/2021 | RENZ SORIANO |
| Construction near power lines | Cleared | 11/2/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Michael N Soumekh; Lic. No.: 773770-B | 1140 SOUTH ALFRED STREET LOS ANGELES, CA 90035 |
| Engineer | Nohroodi,, Nader Gholi; Lic. No.: C36971 | 7389 PERIGORD CT TUJUNGA, CA 91042 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/21/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Underground Mechanical | 3/21/2022 | Approved | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 3/31/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Underground Mechanical | 3/31/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 4/6/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 4/6/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 4/8/2022 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 4/8/2022 | Partial Approval | STUART CHAPMAN |
| Sewer | 4/8/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 4/8/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/19/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 4/22/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 4/26/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 5/19/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 5/26/2022 | Approved | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 7/15/2022 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 7/15/2022 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 7/15/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 7/19/2022 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 7/19/2022 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 7/19/2022 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 7/25/2022 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/3/2022 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Approved | JEFFREY MEAD |
| Green Building Rough | 8/3/2022 | Approved | JEFFREY MEAD |
| HVAC-Rough | 8/3/2022 | Corrections Issued | JEFFREY MEAD |
| Insulation | 8/3/2022 | Corrections Issued | JEFFREY MEAD |
| Interior/Exterior Lathing | 8/3/2022 | Approved | JEFFREY MEAD |
| Shower Pan | 8/3/2022 | Approved | JEFFREY MEAD |
| Insulation | 8/4/2022 | Partial Approval | JEFFREY MEAD |
| Drywall Nailing | 8/8/2022 | Approved | JEFFREY MEAD |
| Insulation | 8/8/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 8/8/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 11/21/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 11/21/2022 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 11/21/2022 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 11/21/2022 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 11/21/2022 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 11/29/2022 | Approved | JEFFREY MEAD |
| Final | 11/29/2022 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 11/29/2022 | Approved | JEFFREY MEAD |
| Smoke Detectors | 11/29/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 2/22/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/22/2023 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/22/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/22/2023 | Approved | ALIZAH MAYAGOITIA |