917 S 3RD AVE 90019

Certificate Information: 917 S 3RD AVE 90019

Application / Permit
21014-10000-02050
Plan Check / Job No.
B21LA07694
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* CONVERSION OF (E) GARAGE & ADDITION FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c)&(d)
Permit Issued
Issued on 1/12/2022
Issuing Office
Current Status
CofO Issued on 2/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 LAMAR DAVIS
Corrections Issued 5/27/2021 LAMAR DAVIS
Quality Review Completed 6/6/2021 HERNAN ARREOLA
Applicant returned to address corrections 8/4/2021 LAMAR DAVIS
Applicant returned to address corrections 12/1/2021 LAMAR DAVIS
Plan Check Approved 1/5/2022 LAMAR DAVIS
Issued 1/12/2022 APPLICANT
Building Plans Picked Up 6/30/2022 APPLICANT
CofO in Progress 2/23/2023 ALIZAH MAYAGOITIA
CofO Issued 2/24/2023 DEROLD HAUFF
Permit Finaled 2/24/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/25/2021 CECILIO NAVARRO
Address approval Cleared 6/29/2021 CECILIO NAVARRO
Sewer availability Cleared 7/2/2021 CECILIO NAVARRO
HPOZ Cleared 10/14/2021 AMANDA KAINER
ZI Cleared 10/14/2021 AMANDA KAINER
Roof/Waste drainage to street Cleared 10/16/2021 RENZ SORIANO
Construction near power lines Cleared 11/2/2021 RIDWAN HARDY

Contact Information

Contractor Michael N Soumekh; Lic. No.: 773770-B 1140 SOUTH ALFRED STREET      LOS ANGELES, CA 90035
Engineer Nohroodi,, Nader Gholi; Lic. No.: C36971 7389 PERIGORD CT      TUJUNGA, CA 91042
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/21/2022 Corrections Issued SHAVONNE ESPINOZA
Underground Mechanical 3/21/2022 Approved SHAVONNE ESPINOZA
Footing/Foundation/Slab 3/31/2022 Partial Inspection SHAVONNE ESPINOZA
Underground Mechanical 3/31/2022 Partial Inspection SHAVONNE ESPINOZA
Footing/Foundation/Slab 4/6/2022 Corrections Issued SHAVONNE ESPINOZA
PLUMBING-Rough 4/6/2022 Corrections Issued SHAVONNE ESPINOZA
Excavation/Setback/Form/Re-Bar 4/8/2022 Partial Approval STUART CHAPMAN
PLUMBING-Rough 4/8/2022 Partial Approval STUART CHAPMAN
Sewer 4/8/2022 Approved STUART CHAPMAN
Underground Mechanical 4/8/2022 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 4/19/2022 Corrections Issued SHAVONNE ESPINOZA
Footing/Foundation/Slab 4/22/2022 Corrections Issued SHAVONNE ESPINOZA
Footing/Foundation/Slab 4/26/2022 Corrections Issued SHAVONNE ESPINOZA
Footing/Foundation/Slab 5/19/2022 Corrections Issued SHAVONNE ESPINOZA
Footing/Foundation/Slab 5/26/2022 Approved SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/2/2022 Corrections Issued SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Approved JEFFREY MEAD
ELECTRICAL-Rough 7/15/2022 Corrections Issued JEFFREY MEAD
HVAC-Rough 7/15/2022 Not Ready for Inspection JEFFREY MEAD
PLUMBING-Rough 7/15/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 7/19/2022 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 7/19/2022 Partial Approval JEFFREY MEAD
Green Building Rough 7/19/2022 Not Ready for Inspection JEFFREY MEAD
HVAC-Rough 7/19/2022 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 7/25/2022 Approved JEFFREY MEAD
Interior/Exterior Lathing 7/25/2022 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 8/3/2022 Corrections Issued JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 8/3/2022 Approved JEFFREY MEAD
Green Building Rough 8/3/2022 Approved JEFFREY MEAD
HVAC-Rough 8/3/2022 Corrections Issued JEFFREY MEAD
Insulation 8/3/2022 Corrections Issued JEFFREY MEAD
Interior/Exterior Lathing 8/3/2022 Approved JEFFREY MEAD
Shower Pan 8/3/2022 Approved JEFFREY MEAD
Insulation 8/4/2022 Partial Approval JEFFREY MEAD
Drywall Nailing 8/8/2022 Approved JEFFREY MEAD
Insulation 8/8/2022 Approved JEFFREY MEAD
Interior/Exterior Lathing 8/8/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 11/21/2022 Not Ready for Inspection JEFFREY MEAD
Final 11/21/2022 Corrections Issued JEFFREY MEAD
Green Building Final 11/21/2022 Not Ready for Inspection JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 11/21/2022 SGSOV Approved JEFFREY MEAD
Smoke Detectors 11/21/2022 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 11/29/2022 Approved JEFFREY MEAD
Final 11/29/2022 Corrections Issued JEFFREY MEAD
Green Building Final 11/29/2022 Approved JEFFREY MEAD
Smoke Detectors 11/29/2022 Approved JEFFREY MEAD
ELECTRICAL-Final 2/22/2023 Approved ALIZAH MAYAGOITIA
Final 2/22/2023 OK to Issue CofO ALIZAH MAYAGOITIA
HVAC-Final 2/22/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 2/22/2023 Approved ALIZAH MAYAGOITIA