12267 N SARAZEN PL 91344

Certificate Information: 12267 N SARAZEN PL 91344

Application / Permit
21014-10000-02048
Plan Check / Job No.
B21LA07692
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan SFD addtiion. new addition 390 sq. ft. to ext'g single family res.
Permit Issued
Issued on 7/22/2021
Issuing Office
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 ARSALAN SHABESTARI
Corrections Issued 5/15/2021 ARSALAN SHABESTARI
Quality Review Completed 5/21/2021 MICHAEL PEREZ
Applicant returned to address corrections 6/29/2021 ARSALAN SHABESTARI
Plan Check Approved 7/19/2021 ARSALAN SHABESTARI
Issued 7/22/2021 APPLICANT
CofO in Progress 2/9/2022 MICHAEL TEMPLE
CofO Issued 2/17/2022 MICHAEL SMITH
Permit Finaled 2/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/29/2021 LEE GUILBEAUX
Sewer availability Cleared 6/29/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/30/2021 LEE GUILBEAUX
Grading Pre-Inspection Cleared 7/1/2021 BRIAN MILLER

Contact Information

Contractor G S Construction; Lic. No.: 540685-B 17116 HALSTED ST      NORTHRIDGE, CA 91325

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/26/2021 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 7/27/2021 Approved MARK JOHNSON
PLUMBING-Rough 7/27/2021 Partial Approval MARK JOHNSON
Underground Mechanical 7/27/2021 Partial Approval MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 9/2/2021 Partial Approval MARK JOHNSON
ELECTRICAL-Rough 9/2/2021 Approved MARK JOHNSON
Green Building Rough 9/2/2021 Approved MARK JOHNSON
HVAC-Rough 9/2/2021 Corrections Issued MARK JOHNSON
Interior/Exterior Lathing 9/2/2021 Approved MARK JOHNSON
PLUMBING-Rough 9/2/2021 Approved MARK JOHNSON
Shower Pan 9/2/2021 Approved MARK JOHNSON
Insulation 9/14/2021 Approved ADAM ESCOTO
BUILDING-Rough-Frame 9/16/2021 Approved ADAM ESCOTO
Drywall Nailing 9/16/2021 Approved ADAM ESCOTO
Final 2/7/2022 OK to Issue CofO MICHAEL TEMPLE
Green Building Final 2/7/2022 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 2/7/2022 SGSOV Approved MICHAEL TEMPLE
Smoke Detectors 2/7/2022 Approved MICHAEL TEMPLE