1831 W 69TH ST 90047

Certificate Information: 1831 W 69TH ST 90047

Application / Permit
21014-10000-02044
Plan Check / Job No.
B21LA07671
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION TO (E) SFD AND INTERIOR REMODEL
Permit Issued
Issued on 9/22/2021
Issuing Office
Current Status
CofO Issued on 10/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2021 APPLICANT
Assigned to Plan Check Engineer 4/30/2021 FARSHAD ALIMOHAMADI
Corrections Issued 5/1/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 5/14/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 7/22/2021 ADAM HEGAZI
Issued 9/22/2021 APPLICANT
Building Plans Picked Up 9/24/2021 APPLICANT
CofO in Progress 10/3/2023 STUART CHAPMAN
Permit Finaled 10/9/2023 DEROLD HAUFF
CofO Issued 10/9/2023 DEROLD HAUFF
Permit Finaled 10/9/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/11/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/12/2021 JEANIE LAM

Contact Information

Contractor Izucar J Construction; Lic. No.: 911420-B 937 E FAIRVIEW BLVD      INGLEWOOD, CA 90302
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/14/2021 Approved FREDDIE RIVERA
Footing/Foundation/Slab 10/14/2021 Not Ready for Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 11/15/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 12/3/2021 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 12/3/2021 Not Ready for Inspection FREDDIE RIVERA
Insulation 12/3/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/10/2022 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 8/8/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 8/8/2022 Approved ENRIQUE MIRELES
Green Building Rough 8/8/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/8/2022 Approved ENRIQUE MIRELES
Insulation 8/25/2022 Approved ENRIQUE MIRELES
Shower Pan 8/25/2022 Approved ENRIQUE MIRELES
Drywall Nailing 9/12/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 9/12/2022 Approved ALIZAH MAYAGOITIA
Final 9/13/2023 Corrections Issued JUSTIN HAWLEY
Footing/Foundation/Slab 9/13/2023 Approved JUSTIN HAWLEY
Green Building Final 9/13/2023 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 9/13/2023 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 9/13/2023 Approved JUSTIN HAWLEY
ELECTRICAL-Final 9/18/2023 Approved STUART CHAPMAN
HVAC-Final 9/18/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 9/18/2023 Approved STUART CHAPMAN
Final 10/3/2023 OK to Issue CofO STUART CHAPMAN
Green Building Final 10/3/2023 Approved STUART CHAPMAN
HVAC-Final 10/3/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/3/2023 SGSOV Approved STUART CHAPMAN