2815 S HOLT AVE 90034
Certificate Information: 2815 S HOLT AVE 90034
- Application / Permit
- 21014-10000-02037
- Plan Check / Job No.
- B21LA07653
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREGULAR SHAPED ADDITION TO (E) SFD AT REAR TO EXTEND BEDROOM, BATHROOM, KITCHEN, AND ONE NEW BATHROOM. AND, MINOR REMODEL OF (E) SFD
- Permit Issued
- Issued on 6/1/2021
- Issuing Office
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | GEORGE ALVAREZ |
| Corrections Issued | 5/3/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 5/20/2021 | GEORGE ALVAREZ |
| Issued | 6/1/2021 | APPLICANT |
| Building Plans Picked Up | 6/1/2021 | APPLICANT |
| CofO in Progress | 8/19/2022 | EVAN COOPER |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
| CofO Issued | 8/30/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/11/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 5/11/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/3/2022 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 2/10/2022 | Partial Approval | EVAN COOPER |
| Insulation | 2/10/2022 | Partial Approval | EVAN COOPER |
| Deputy Drilled-In Anchors | 2/15/2022 | Conditional Approval | EVAN COOPER |
| Deputy Wood Construction | 2/15/2022 | Conditional Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 2/16/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 2/28/2022 | Partial Approval | EVAN COOPER |
| Wood Frame | 2/28/2022 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 5/4/2022 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2022 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 5/17/2022 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 5/25/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 5/25/2022 | Approved | EVAN COOPER |
| Green Building Rough | 5/25/2022 | Approved | EVAN COOPER |
| HVAC-Rough | 5/25/2022 | Approved | EVAN COOPER |
| MERV13>=Rough | 5/25/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 5/25/2022 | Approved | EVAN COOPER |
| Green Building Rough | 5/27/2022 | Approved | EVAN COOPER |
| Insulation | 5/27/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 6/2/2022 | Approved | KEVIN SARGSYAN |
| Final | 8/17/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 8/17/2022 | Approved | EVAN COOPER |
| Green Building Final | 8/17/2022 | Approved | EVAN COOPER |
| MERV13>=Final | 8/17/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 8/17/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/19/2022 | Approved | EVAN COOPER |
| Final | 8/19/2022 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 8/19/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 8/19/2022 | Approved | EVAN COOPER |