5134 S RUTHELEN ST 90062

Certificate Information: 5134 S RUTHELEN ST 90062

Application / Permit
21014-10000-02028
Plan Check / Job No.
B21LA07622
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION
Permit Issued
Issued on 7/14/2021
Issuing Office
Current Status
CofO Issued on 1/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 GEORGE ALVAREZ
Corrections Issued 4/29/2021 GEORGE ALVAREZ
Plan Check Approved 6/11/2021 SINA KHOSRAVI
Issued 7/14/2021 APPLICANT
Building Plans Picked Up 8/23/2021 APPLICANT
CofO in Progress 1/4/2023 SABAS ALONSO
Permit Finaled 1/7/2023 DEROLD HAUFF
CofO Issued 1/7/2023 DEROLD HAUFF
Permit Finaled 1/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/17/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 5/17/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 5/17/2021 CECILIO NAVARRO
Sewer availability Cleared 5/17/2021 CECILIO NAVARRO

Contact Information

Architect Youssefian,, Sam H; Lic. No.: C12562 1431 HUNTINGTON DR #201      SOUTH PASADENA, CA 91030
Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/29/2021 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 9/29/2021 Conditional Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 10/5/2021 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 10/7/2021 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Partial Approval SABAS ALONSO
PLUMBING-Rough 12/3/2021 Not Ready for Inspection SABAS ALONSO
Sewer 3/8/2022 Approved SABAS ALONSO
Underground Mechanical 3/8/2022 Partial Approval SABAS ALONSO
Pre-Inspection 5/19/2022 Partial Inspection SABAS ALONSO
BUILDING-Rough-Frame 6/1/2022 Corrections Issued HORACE FULTZ
ELECTRICAL-Rough 6/1/2022 Not Ready for Inspection HORACE FULTZ
Green Building Rough 6/1/2022 Approved HORACE FULTZ
PLUMBING-Rough 6/1/2022 Corrections Issued HORACE FULTZ
ELECTRICAL-Rough 6/7/2022 Approved HORACE FULTZ
HVAC-Rough 6/7/2022 Approved HORACE FULTZ
PLUMBING-Rough 6/7/2022 Approved HORACE FULTZ
Wood Frame 6/7/2022 Corrections Issued HORACE FULTZ
BUILDING-Rough-Frame 6/27/2022 Approved SABAS ALONSO
Wood Frame 6/27/2022 Approved SABAS ALONSO
Insulation 7/7/2022 Partial Approval HORACE FULTZ
Shower Pan 7/7/2022 Corrections Issued HORACE FULTZ
Insulation 7/14/2022 Approved SABAS ALONSO
Shower Pan 7/14/2022 Approved SABAS ALONSO
Drywall Nailing 7/27/2022 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Not Ready for Inspection HORACE FULTZ
Interior/Exterior Lathing 8/10/2022 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 8/26/2022 Approved RYAN SALAZAR
Final 11/3/2022 Corrections Issued SABAS ALONSO
Green Building Final 11/3/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/3/2022 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 11/3/2022 Approved SABAS ALONSO
Final 12/2/2022 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Approved SABAS ALONSO
Final 12/22/2022 OK to Issue CofO SABAS ALONSO