5134 S RUTHELEN ST 90062
Certificate Information: 5134 S RUTHELEN ST 90062
- Application / Permit
- 21014-10000-02028
- Plan Check / Job No.
- B21LA07622
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION
- Permit Issued
- Issued on 7/14/2021
- Issuing Office
- Current Status
- CofO Issued on 1/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | GEORGE ALVAREZ |
| Corrections Issued | 4/29/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 6/11/2021 | SINA KHOSRAVI |
| Issued | 7/14/2021 | APPLICANT |
| Building Plans Picked Up | 8/23/2021 | APPLICANT |
| CofO in Progress | 1/4/2023 | SABAS ALONSO |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
| CofO Issued | 1/7/2023 | DEROLD HAUFF |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/17/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 5/17/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 5/17/2021 | CECILIO NAVARRO |
Contact Information
| Architect | Youssefian,, Sam H; Lic. No.: C12562 | 1431 HUNTINGTON DR #201 SOUTH PASADENA, CA 91030 |
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/29/2021 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 9/29/2021 | Conditional Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 10/5/2021 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 10/7/2021 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2021 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 12/3/2021 | Not Ready for Inspection | SABAS ALONSO |
| Sewer | 3/8/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/8/2022 | Partial Approval | SABAS ALONSO |
| Pre-Inspection | 5/19/2022 | Partial Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/1/2022 | Corrections Issued | HORACE FULTZ |
| ELECTRICAL-Rough | 6/1/2022 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Rough | 6/1/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 6/1/2022 | Corrections Issued | HORACE FULTZ |
| ELECTRICAL-Rough | 6/7/2022 | Approved | HORACE FULTZ |
| HVAC-Rough | 6/7/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 6/7/2022 | Approved | HORACE FULTZ |
| Wood Frame | 6/7/2022 | Corrections Issued | HORACE FULTZ |
| BUILDING-Rough-Frame | 6/27/2022 | Approved | SABAS ALONSO |
| Wood Frame | 6/27/2022 | Approved | SABAS ALONSO |
| Insulation | 7/7/2022 | Partial Approval | HORACE FULTZ |
| Shower Pan | 7/7/2022 | Corrections Issued | HORACE FULTZ |
| Insulation | 7/14/2022 | Approved | SABAS ALONSO |
| Shower Pan | 7/14/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 7/27/2022 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Not Ready for Inspection | HORACE FULTZ |
| Interior/Exterior Lathing | 8/10/2022 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 8/26/2022 | Approved | RYAN SALAZAR |
| Final | 11/3/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 11/3/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/3/2022 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 11/3/2022 | Approved | SABAS ALONSO |
| Final | 12/2/2022 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Approved | SABAS ALONSO |
| Final | 12/22/2022 | OK to Issue CofO | SABAS ALONSO |