8100 S AIRLANE AVE 90045
Certificate Information: 8100 S AIRLANE AVE 90045
- Application / Permit
- 21014-10000-02025
- Plan Check / Job No.
- B21LA07608
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AT REAR OF (E) SFD. '' THE LID CLEARANCE HAS BEEN DEFERRED. APPROVAL FOR LID REQUIREMENTS SHALL BE OBTAINED FROM LASAN PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF OCCUPANCY''
- Permit Issued
- Issued on 9/27/2021
- Issuing Office
- Current Status
- CofO Issued on 6/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 5/12/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 5/14/2021 | FARUK SEZER |
| Applicant returned to address corrections | 8/13/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 9/9/2021 | SERGIO GUTIERREZ |
| Issued | 9/27/2021 | APPLICANT |
| Building Plans Picked Up | 9/28/2021 | APPLICANT |
| CofO in Progress | 6/1/2022 | BOBBY KEY |
| Permit Finaled | 6/7/2022 | DANIEL ORRANTE |
| CofO Issued | 6/7/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/7/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/21/2021 | GILBERT URREA |
| Specific Plan | Cleared | 8/9/2021 | KEVIN ARUCAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2021 | DINAH GARIN |
| Sewer availability | Cleared | 8/13/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 9/3/2021 | TRACY TATE |
Contact Information
| Contractor | Izucar J Construction; Lic. No.: 911420-B | 937 E FAIRVIEW BLVD INGLEWOOD, CA 90302 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/29/2021 | Conditional Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 9/30/2021 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/5/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 10/25/2021 | Partial Inspection | DAVID FEILER |
| PLUMBING-Rough | 10/28/2021 | Partial Approval | BOBBY KEY |
| Pre-Inspection | 10/28/2021 | Partial Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2021 | Approved | ENRIQUE MIRELES |
| Wood Frame | 11/12/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/23/2021 | Approved | JOHN KAYON |
| Green Building Rough | 11/23/2021 | Approved | JOHN KAYON |
| Interior/Exterior Lathing | 11/23/2021 | Approved | JOHN KAYON |
| PLUMBING-Rough | 11/23/2021 | Approved | JOHN KAYON |
| Shower Pan | 11/23/2021 | Approved | JOHN KAYON |
| ELECTRICAL-Rough | 11/30/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Interior/Exterior Lathing | 11/30/2021 | Partial Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 12/6/2021 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 12/10/2021 | Corrections Issued | JOHN KAYON |
| Insulation | 12/10/2021 | Approved | JOHN KAYON |
| Drywall Nailing | 12/17/2021 | Approved | BOBBY KEY |
| Final | 12/17/2021 | Corrections Issued | BOBBY KEY |
| Pre-Inspection | 3/25/2022 | Partial Inspection | BOBBY KEY |
| Underground Mechanical | 4/4/2022 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Final | 4/26/2022 | Approved | BOBBY KEY |
| Final | 4/26/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 4/26/2022 | Approved | BOBBY KEY |
| HVAC-Final | 4/26/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 4/26/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/26/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 4/26/2022 | Approved | BOBBY KEY |
| Deck | 5/4/2022 | Partial Approval | BOBBY KEY |
| HVAC-Final | 5/4/2022 | Approved | BOBBY KEY |
| Deck | 5/11/2022 | Approved | BOBBY KEY |
| Final | 5/26/2022 | Not Ready for Inspection | BOBBY KEY |
| Final | 6/1/2022 | OK to Issue CofO | BOBBY KEY |