3685 S EDGEHILL DR 90018

Certificate Information: 3685 S EDGEHILL DR 90018

Application / Permit
21014-10000-02016
Plan Check / Job No.
B21LA07582
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1-STORY MASTER BEDROOM AND BATHROOM ADDITION
Permit Issued
Issued on 10/18/2021
Issuing Office
Current Status
Issued on 10/18/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/23/2021 APPLICANT
Assigned to Plan Check Engineer 4/28/2021 SINA KHOSRAVI
Corrections Issued 4/29/2021 SINA KHOSRAVI
Applicant returned to address corrections 7/3/2021 SAMUEL GONZALEZ
Applicant returned to address corrections 7/22/2021 DANIEL YIP
Plan Check Approved 7/22/2021 DANIEL YIP
No Progress 7/22/2021 DANIEL YIP
Plan Check Approved 7/27/2021 DANIEL YIP
Building Plans Picked Up 7/30/2021 APPLICANT
Issued 10/18/2021 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/15/2021 RENZ SORIANO
Sewer availability Cleared 6/15/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 6/16/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/21/2021 No Access for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 11/17/2021 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 11/23/2021 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/7/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/24/2022 Approved ANTHONY EGSON
Footing/Foundation/Slab 5/24/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 6/2/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 7/13/2022 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 7/13/2022 Approved ANTHONY EGSON
PLUMBING-Rough 7/13/2022 Corrections Issued ANTHONY EGSON
Underground Mechanical 7/13/2022 Approved ANTHONY EGSON
ELECTRICAL-Rough 8/1/2022 Approved ANTHONY EGSON
PLUMBING-Rough 8/1/2022 Approved ANTHONY EGSON
Drywall Nailing 8/17/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 9/21/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 9/29/2022 Approved ANTHONY EGSON
Shower Pan 9/29/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 12/6/2022 Approved ANTHONY EGSON
Final 12/6/2022 Conditional Approval ANTHONY EGSON
Green Building Final 12/6/2022 Approved ANTHONY EGSON
Green Building Rough 12/6/2022 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Approved ANTHONY EGSON
Smoke Detectors 12/6/2022 Approved ANTHONY EGSON