211 S VETERAN AVE 90024

Certificate Information: 211 S VETERAN AVE 90024

Application / Permit
21014-10000-02015
Plan Check / Job No.
B21LA07577
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story SFD with attached 2-car garage. Fire sprinkler system is provided throughout the building.
Permit Issued
Issued on 12/15/2021
Issuing Office
Current Status
CofO Issued on 10/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 HELEN NGUYEN
Corrections Issued 6/8/2021 HELEN NGUYEN
Quality Review Completed 6/17/2021 MICHAEL PEREZ
Building Plans Picked Up 6/18/2021 APPLICANT
Applicant returned to address corrections 11/8/2021 HELEN NGUYEN
Plan Check Approved 12/15/2021 HELEN NGUYEN
Issued 12/15/2021 APPLICANT
CofO in Progress 9/30/2022 RICHARD STEINBACH
Permit Finaled 10/3/2022 DANIEL ORRANTE
CofO Issued 10/3/2022 DANIEL ORRANTE
Permit Finaled 10/3/2022 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 7/23/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 7/26/2021 ANTHONY MAINEZ
Specific Plan Cleared 8/25/2021 VALERIA CEJA
Watercourse Cleared 9/1/2021 MAHELET GEBEYHU
Hydrant and Access approval Cleared 9/19/2021 ROBERT DUFF
Low Impact Development Cleared 10/15/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 10/25/2021 ANTHONY MAINEZ
GPI Written Notices Cleared 11/8/2021 HELEN NGUYEN
Grading Pre-Inspection Cleared 11/8/2021 HELEN NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/22/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/31/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 2/8/2022 Corrections Issued BRENDAN LOONEY
FLOOD-Proofing Certificate 2/8/2022 Approved BRENDAN LOONEY
Green Building Rough 2/8/2022 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 2/8/2022 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 2/10/2022 Partial Inspection BRENDAN LOONEY
Deputy Wood Construction 2/18/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Wood Frame 2/22/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Gas Test 3/18/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 3/18/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 3/22/2022 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 3/24/2022 Approved CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/24/2022 Corrections Issued CHRISTOPHER WILSON
Shower Pan 3/24/2022 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/5/2022 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/5/2022 Approved CARLOS MATAMOROS
Green Building Rough 4/5/2022 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 4/5/2022 Approved CARLOS MATAMOROS
PLUMBING-Rough 4/5/2022 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 4/5/2022 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 4/27/2022 Approved CARLOS MATAMOROS
Insulation 5/10/2022 Approved CLAYTON GRAHAM
Drywall Nailing 5/23/2022 Approved BRENDAN LOONEY
Green Building Rough 5/23/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 5/23/2022 Partial Approval BRENDAN LOONEY
PLUMBING-Final 9/1/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 9/2/2022 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 9/2/2022 Approved CARLOS MATAMOROS
Service/Power Release 9/2/2022 Approved CARLOS MATAMOROS
ELECTRICAL-Final 9/7/2022 Not Ready for Inspection CARLOS MATAMOROS
Gas Test 9/7/2022 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 9/28/2022 Approved CARLOS MATAMOROS
Final 9/28/2022 Conditional Approval CARLOS MATAMOROS
Green Building Final 9/28/2022 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/28/2022 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 9/28/2022 Approved CARLOS MATAMOROS
Final 9/30/2022 OK to Issue CofO MICHAEL PELHAM