4413 W 64TH ST 90043
Certificate Information: 4413 W 64TH ST 90043
- Application / Permit
- 21014-10000-02011
- Plan Check / Job No.
- B21LA07573
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SFD AND INTERIOR REMODEL
- Permit Issued
- Issued on 2/7/2022
- Issuing Office
- Current Status
- CofO Issued on 7/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2021 | SINA KHOSRAVI |
| Corrections Issued | 4/28/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 9/8/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 9/24/2021 | LUKE GONZALES |
| Plan Check Approved | 10/1/2021 | LUKE GONZALES |
| Building Plans Picked Up | 10/5/2021 | APPLICANT |
| Issued | 2/7/2022 | APPLICANT |
| CofO in Progress | 7/21/2022 | ENRIQUE MIRELES |
| Permit Finaled | 7/27/2022 | DEROLD HAUFF |
| CofO Issued | 7/27/2022 | DEROLD HAUFF |
| Permit Finaled | 7/27/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/8/2021 | SINA KHOSRAVI |
| Roof/Waste drainage to street | Cleared | 9/19/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2021 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adefeso,, Wole Dayo; Lic. No.: C63361 | 1620 CENTINELA AVE 3048 INGLEWOOD, CA 90302 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/22/2022 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 3/24/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/30/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/4/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 4/4/2022 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 4/21/2022 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/21/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Drywall Nailing | 5/11/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 5/11/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/11/2022 | Corrections Issued | ENRIQUE MIRELES |
| Insulation | 5/16/2022 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 5/16/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 5/19/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/19/2022 | Corrections Issued | ENRIQUE MIRELES |
| Drywall Nailing | 5/24/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/24/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/27/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/11/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/11/2022 | Approved | ENRIQUE MIRELES |
| Final | 7/11/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 7/11/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 7/11/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 7/11/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 7/11/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 7/11/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/18/2022 | Approved | ENRIQUE MIRELES |
| Final | 7/18/2022 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 7/18/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 7/18/2022 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 7/18/2022 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 7/20/2022 | Approved | ENRIQUE MIRELES |
| Final | 7/21/2022 | OK to Issue CofO | ENRIQUE MIRELES |