18722 1/2 W LANARK ST 91335
Certificate Information: 18722 1/2 W LANARK ST 91335
- Application / Permit
- 21014-10000-02001
- Plan Check / Job No.
- B21LA07527
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-PLAN: PROPOSED ADDITION TO EXISTING ALQ TO CREATE AN ACCESSORY DWELLING UNIT PER ORDINANCE. ***SEE COMMENTS*** "COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 06/19/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 9/24/2021
- Issuing Office
- Current Status
- CofO Issued on 8/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | MICHAEL LOPEZ |
| Corrections Issued | 6/11/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 6/17/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/6/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 8/27/2021 | MICHAEL LOPEZ |
| Issued | 9/24/2021 | APPLICANT |
| CofO in Progress | 6/24/2022 | VINCENT HANLEY |
| Permit Finaled | 8/17/2022 | JOHN JANSON |
| CofO Issued | 8/17/2022 | JOHN JANSON |
| Permit Finaled | 8/17/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/18/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 6/18/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/22/2021 | ADRIAN CASTRO |
Contact Information
| Architect | Hanna,, Remon; Lic. No.: C36271 | 26030 SANDBURG PL STEVENSON RANCH, CA 91381 |
| Contractor | Owner-Builder | , |
| Engineer | Hanna,, Emil R; Lic. No.: C63602 | 18925 GRANADA CIRCLE NORTHRIDGE, CA 91326 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/17/2021 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 11/22/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 11/22/2021 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/14/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/14/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/14/2022 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 1/14/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/24/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/24/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/24/2022 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 1/24/2022 | Approved | VINCENT HANLEY |
| Insulation | 1/31/2022 | Conditional Approval | JUSTIN HAWLEY |
| Drywall Nailing | 2/4/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/4/2022 | Approved | VINCENT HANLEY |
| Gas Test | 3/10/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 4/20/2022 | Corrections Issued | VINCENT HANLEY |
| Final | 4/20/2022 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/20/2022 | Approved | VINCENT HANLEY |
| Green Building Final | 4/20/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/20/2022 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/20/2022 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 4/20/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/2/2022 | Approved | VINCENT HANLEY |
| Final | 6/2/2022 | Partial Inspection | VINCENT HANLEY |
| HVAC-Final | 6/2/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 6/2/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/2/2022 | SGSOV Approved | VINCENT HANLEY |
| Final | 6/24/2022 | OK to Issue CofO | VINCENT HANLEY |