6023-6025 N TUJUNGA AVE 91606
Certificate Information: 6023-6025 N TUJUNGA AVE 91606
- Application / Permit
- 21014-10000-01998
- Plan Check / Job No.
- B21LA07515
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT PORTION OF DUPLEX INTO A NEW ADU 346 SQ FT PROPSED NEW COVERED PATIO ON THE 1ST FLOOR AND DECK ON THE 2ND FLOOR WITH TRELLIS ROOF. PER ENGINEER DESIGN (ATTACHED ADU PER ORDINANCE LAMC 12.22 A 33(C) AND (E))
- Permit Issued
- Issued on 3/8/2022
- Issuing Office
- Current Status
- CofO Issued on 2/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | AUNG SOE |
| Corrections Issued | 5/3/2021 | AUNG SOE |
| Applicant returned to address corrections | 12/16/2021 | LUKE GONZALES |
| Plan Check Approved | 1/28/2022 | ADAM HEGAZI |
| Issued | 3/8/2022 | APPLICANT |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| CofO in Progress | 1/31/2023 | JOHN HAYES |
| Permit Finaled | 2/17/2023 | MICHAEL SMITH |
| CofO Issued | 2/17/2023 | MICHAEL SMITH |
| Permit Finaled | 2/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/19/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/19/2021 | CARLOS AGUILERA |
| Tenant Habitability Plan | Cleared | 7/12/2021 | PHILLIP MUNGUIA |
| "Q" conditions | Cleared | 8/9/2021 | RUBEN VASQUEZ |
| Hydrant and Access approval | Cleared | 10/13/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 4/27/2022 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/17/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 11/17/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 11/17/2022 | Approved | JOHN HAYES |
| PLUMBING-Rough | 11/17/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 12/7/2022 | Approved | JOHN HAYES |
| Green Building Rough | 12/7/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 12/7/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 12/19/2022 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 1/11/2023 | SGSOV Not Ready | JOHN HAYES |
| Special/Order Compliance | 1/11/2023 | Corrections Issued | JOHN HAYES |
| Final | 1/24/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 1/24/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 1/24/2023 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 1/24/2023 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 1/24/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/31/2023 | OK to Issue CofO | JOHN HAYES |
| Footing/Foundation/Slab | 1/31/2023 | Approved | JOHN HAYES |
| Green Building Final | 1/31/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/31/2023 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 1/31/2023 | Approved | JOHN HAYES |
| Wood Frame | 1/31/2023 | Approved | JOHN HAYES |