8417 1/2 W GRENOBLE ST 91040

Certificate Information: 8417 1/2 W GRENOBLE ST 91040

Application / Permit
21014-10000-01973
Plan Check / Job No.
B21LA07434
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1-STORY BEDROOMS AND BATHROOM ADDITION TO REAR UNIT PER EOR DESIGN
Permit Issued
Issued on 8/3/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2021 APPLICANT
Assigned to Plan Check Engineer 5/3/2021 LAWRENCE QUIRANTE
Corrections Issued 5/4/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 5/20/2021 LAWRENCE QUIRANTE
Building Plans Picked Up 5/25/2021 APPLICANT
Applicant returned to address corrections 10/17/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 1/4/2023 WEIJIAN HUANG
Plan Check Approved 2/24/2023 DANIEL SANJUAN
Issued 8/3/2023 APPLICANT
CofO in Progress 3/11/2025 WILLIAM WREN
Permit Finaled 3/17/2025 RUBEN SALAS
CofO Issued 3/17/2025 RUBEN SALAS
Permit Finaled 3/17/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/14/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/14/2021 CARLOS AGUILERA
Sewer availability Cleared 6/14/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 10/3/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/7/2023 Corrections Issued WILLIAM WREN
Pre-Inspection 8/27/2024 Not Ready for Inspection SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 9/5/2024 Approved WILLIAM WREN
Footing/Foundation/Slab 9/12/2024 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 9/17/2024 Corrections Issued WILLIAM WREN
Deputy Reinf. Concrete 9/19/2024 Conditional Approval DAVID MATSON
PLUMBING-Rough 9/24/2024 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Partial Approval WILLIAM WREN
Deputy Wood Construction 10/7/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 10/17/2024 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 10/18/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/18/2024 Approved WILLIAM WREN
PLUMBING-Rough 10/18/2024 Approved WILLIAM WREN
Underground Mechanical 10/21/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/25/2024 Approved WILLIAM WREN
Green Building Rough 10/25/2024 Approved WILLIAM WREN
HVAC-Rough 10/25/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 10/25/2024 Approved WILLIAM WREN
Insulation 10/29/2024 Approved WILLIAM WREN
Drywall Nailing 11/15/2024 Approved WILLIAM WREN
Shower Pan 11/15/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 12/11/2024 Approved WILLIAM WREN
ELECTRICAL-Final 12/24/2024 Corrections Issued MATTHEW NELSON
Final 2/26/2025 OK to Issue CofO WILLIAM WREN
Footing/Foundation/Slab 2/26/2025 Approved WILLIAM WREN
Green Building Final 2/26/2025 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Approved WILLIAM WREN
Smoke Detectors 2/26/2025 Approved WILLIAM WREN