1332 W YOSEMITE DR 90041
Certificate Information: 1332 W YOSEMITE DR 90041
- Application / Permit
- 21014-10000-01971
- Plan Check / Job No.
- B21LA07433
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- RENOVATION/SECOND STORY ADDITION TO (E) SFD
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | CARLOS MONTES |
| Corrections Issued | 6/2/2021 | CARLOS MONTES |
| Quality Review Completed | 6/9/2021 | WING SUEN |
| Building Plans Picked Up | 6/14/2021 | APPLICANT |
| Applicant returned to address corrections | 2/15/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 4/5/2022 | CARLOS MONTES |
| Plan Check Approved | 4/14/2022 | CARLOS MONTES |
| Issued | 5/18/2022 | APPLICANT |
| CofO in Progress | 7/31/2025 | SCOTT FINNILA |
| Permit Finaled | 8/1/2025 | DEROLD HAUFF |
| CofO Issued | 8/1/2025 | DEROLD HAUFF |
| Permit Finaled | 8/1/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2021 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 11/18/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 2/2/2022 | JEANIE LAM |
| Sewer availability | Cleared | 3/7/2022 | AMAAN MALIK |
| GPI Written Notices | Cleared | 4/14/2022 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 4/14/2022 | CARLOS MONTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rivera,, Bobby Zulueta; Lic. No.: C77218 | 14703 HELWIG AVE NORWALK, CA 90650 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/20/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/23/2022 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/26/2022 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 11/15/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/15/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 11/15/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/15/2022 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 11/15/2022 | Corrections Issued | CRAIG VAUGHAN |
| Wood Frame | 11/15/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/28/2022 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 11/28/2022 | Approved | CRAIG VAUGHAN |
| Wood Frame | 11/28/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/7/2022 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Corrections Issued | SCOTT FINNILA |
| Wood Frame | 12/7/2022 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 12/8/2022 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 12/16/2022 | Partial Approval | SCOTT FINNILA |
| Insulation | 12/16/2022 | Partial Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 12/16/2022 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/22/2022 | Approved | SCOTT FINNILA |
| Insulation | 12/22/2022 | Approved | SCOTT FINNILA |
| Drywall Nailing | 12/30/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 1/4/2023 | Approved | JEFFREY MEAD |
| Shower Pan | 1/4/2023 | Approved | JEFFREY MEAD |
| Sewer | 3/8/2023 | Approved | OSVALDO PARAMO |
| Service/Power Release | 5/10/2023 | Corrections Issued | CRAIG VAUGHAN |
| Service/Power Release | 5/16/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/17/2023 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/17/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/17/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/17/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/12/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 9/19/2023 | Approved | ROY SPAULDING |
| PLUMBING-Final | 3/21/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/2/2024 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 4/2/2024 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Final | 5/2/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 5/2/2024 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/17/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/17/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 7/17/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 7/17/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/17/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 7/17/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 7/30/2025 | OK to Issue CofO | SCOTT FINNILA |
| Green Building Final | 7/30/2025 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 7/30/2025 | Approved | SCOTT FINNILA |