736 N ROBINSON ST 90026

Certificate Information: 736 N ROBINSON ST 90026

Application / Permit
21014-10000-01968
Plan Check / Job No.
B21LA07394
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
190 SF SECOND STORY ADDITION AND REMODELING EXISTING BUILDING INCLUDING NEW ATTACHED PERMEABLE UNCOVERED DECK TO REAR OF THE BUILDING.
Permit Issued
Issued on 11/3/2021
Issuing Office
Current Status
CofO Issued on 2/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2021 APPLICANT
Assigned to Plan Check Engineer 5/6/2021 YOUNG KIM
Corrections Issued 5/14/2021 YOUNG KIM
Quality Review Completed 5/14/2021 SAI KHUM
Applicant returned to address corrections 6/29/2021 YOUNG KIM
Plan Check Approved 8/6/2021 YOUNG KIM
Issued 11/3/2021 APPLICANT
Building Plans Picked Up 11/15/2021 APPLICANT
CofO in Progress 2/10/2023 FREDDIE RIVERA
CofO Issued 2/15/2023 DEROLD HAUFF
Permit Finaled 2/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 6/3/2021 TA ANH
Grading Pre-Inspection Cleared 6/7/2021 BRIAN MILLER
Roof/Waste drainage to street Cleared 6/7/2021 WALLIE JONG
Sewer availability Cleared 6/7/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/8/2021 WALLIE JONG

Contact Information

Architect Kim,, Peter Sung Taek; Lic. No.: C29012 1920 LEMYONE ST.      LOS ANGELES, CA 90026
Contractor Malkoe Design Llc; Lic. No.: 895875-B 3123 VERDUGO PLACE      LOS ANGELES, CA 90065
Engineer Kwon,, Ohsung; Lic. No.: C85429 2129 ASCOT DR APT 14      MORAGA, CA 94556

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/9/2021 Partial Approval RUBEN SALAS
Footing/Foundation/Slab 12/14/2021 Corrections Issued ALIZAH MAYAGOITIA
METHANE-Barrier 12/14/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
METHANE-Subgrade 12/14/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 12/21/2021 Corrections Issued ALIZAH MAYAGOITIA
METHANE-Barrier 12/21/2021 Approved ALIZAH MAYAGOITIA
METHANE-Subgrade 12/21/2021 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 1/7/2022 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Approved AMY COLIN
BUILDING-Rough-Frame 3/21/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 3/21/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 3/21/2022 Approved ALIZAH MAYAGOITIA
Green Building Rough 3/21/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 3/21/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
METHANE-Rough 3/21/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 3/21/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/29/2022 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 3/29/2022 Approved FREDDIE RIVERA
Gas Test 3/29/2022 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 3/29/2022 Conditional Approval FREDDIE RIVERA
HVAC-Rough 3/29/2022 Approved FREDDIE RIVERA
Shower Pan 3/29/2022 Not Ready for Inspection FREDDIE RIVERA
Gas Test 4/5/2022 Approved FREDDIE RIVERA
Insulation 4/5/2022 Approved FREDDIE RIVERA
Shower Pan 4/5/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 4/18/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/18/2022 Conditional Approval FREDDIE RIVERA
Green Building Rough 4/18/2022 Approved FREDDIE RIVERA
Deputy Wood Construction 4/19/2022 Conditional Approval FREDDIE RIVERA
Drywall Nailing 4/28/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 4/28/2022 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 5/3/2022 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Final 10/6/2022 Approved FREDDIE RIVERA
Final 10/6/2022 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 10/6/2022 Approved FREDDIE RIVERA
Green Building Final 10/6/2022 Approved FREDDIE RIVERA
PLUMBING-Final 10/6/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 10/6/2022 Approved FREDDIE RIVERA
Final 12/5/2022 Conditional Approval FREDDIE RIVERA
Final 1/11/2023 Corrections Issued FREDDIE RIVERA
Final 2/10/2023 OK to Issue CofO FREDDIE RIVERA