13132 W CANTARA ST 91605

Certificate Information: 13132 W CANTARA ST 91605

Application / Permit
21014-10000-01959
Plan Check / Job No.
B21LA07341
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE TO ADU WITH AN ADDITION DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 8/14/2025
Issuing Office
Current Status
Issued on 8/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/21/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 CARLOS MONTES
Corrections Issued 5/30/2021 CARLOS MONTES
Quality Review Completed 6/9/2021 WING SUEN
Applicant returned to address corrections 12/22/2021 CARLOS MONTES
Applicant returned to address corrections 7/22/2022 CARLOS MONTES
Plan Check Approved 8/23/2022 CARLOS MONTES
Issued 8/14/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/17/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/17/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 6/17/2021 DAGOVERTO GUERRERO
ZA Case Cleared 6/17/2021 MIGUEL GAMBOA
Roof/Waste drainage to street Cleared 12/23/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Rent Ready Construction Inc; Lic. No.: 1065376-B       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/6/2026 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 1/9/2026 Approved OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 1/16/2026 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 1/16/2026 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 1/26/2026 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 3/18/2026 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 3/27/2026 Approved GAREN HAYRAPETYAN
HVAC-Rough 3/27/2026 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 3/27/2026 Approved GAREN HAYRAPETYAN
Underground Mechanical 3/27/2026 Partial Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 4/7/2026 Approved OGANES TARAKHCHYAN
Green Building Rough 4/7/2026 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 4/7/2026 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/20/2026 Approved GAREN HAYRAPETYAN
Green Building Rough 4/20/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 4/20/2026 Corrections Issued GAREN HAYRAPETYAN
Insulation 4/28/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/28/2026 Partial Approval OGANES TARAKHCHYAN
Wood Frame 4/28/2026 Approved OGANES TARAKHCHYAN
Drywall Nailing 5/4/2026 Approved RAUL OLAGI
Shower Pan 5/4/2026 Approved RAUL OLAGI
Interior/Exterior Lathing 5/7/2026 Approved OGANES TARAKHCHYAN