1541 1/2 W 59TH ST 90047
Certificate Information: 1541 1/2 W 59TH ST 90047
- Application / Permit
- 21014-10000-01957
- Plan Check / Job No.
- B21LA07334
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTING EXISTING GARAGE TO NEW ADU PER DETACHED ADU STATE LAW (1-STORY)
- Permit Issued
- Issued on 2/17/2022
- Issuing Office
- Current Status
- CofO Issued on 9/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | CARLOS MONTES |
| Corrections Issued | 6/1/2021 | CARLOS MONTES |
| Quality Review Completed | 6/9/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/20/2021 | CARLOS MONTES |
| Plan Check Approved | 10/28/2021 | CARLOS MONTES |
| Issued | 2/17/2022 | APPLICANT |
| CofO in Progress | 8/14/2024 | CRAIG DAVIS |
| Permit Finaled | 9/3/2024 | RUBEN SALAS |
| CofO Issued | 9/3/2024 | RUBEN SALAS |
| Permit Finaled | 9/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/13/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2021 | JEANIE LAM |
| Sewer availability | Cleared | 7/28/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/25/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/13/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/31/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 6/14/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/28/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 6/28/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/28/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 7/13/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/4/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 12/21/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Shower Pan | 12/21/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Gas Test | 12/27/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Sewer | 12/27/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Shower Pan | 12/27/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Sewer | 3/1/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Shower Pan | 3/1/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 3/29/2023 | Corrections Issued | ENRIQUE MIRELES |
| Gas Test | 4/5/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 4/5/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/28/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/28/2023 | Approved | ENRIQUE MIRELES |
| Final | 7/28/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 7/28/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 7/28/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 7/28/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 7/28/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 8/18/2023 | Approved | ENRIQUE MIRELES |
| Final | 8/18/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 8/18/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 8/31/2023 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 9/5/2023 | Approved | ENRIQUE MIRELES |
| Final | 5/21/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 6/25/2024 | Partial Approval | CRAIG DAVIS |
| Final | 7/3/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 8/13/2024 | OK to Issue CofO | CRAIG DAVIS |
| Service/Power Release | 8/13/2024 | Approved | CRAIG DAVIS |