1541 1/2 W 59TH ST 90047

Certificate Information: 1541 1/2 W 59TH ST 90047

Application / Permit
21014-10000-01957
Plan Check / Job No.
B21LA07334
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING EXISTING GARAGE TO NEW ADU PER DETACHED ADU STATE LAW (1-STORY)
Permit Issued
Issued on 2/17/2022
Issuing Office
Current Status
CofO Issued on 9/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 CARLOS MONTES
Corrections Issued 6/1/2021 CARLOS MONTES
Quality Review Completed 6/9/2021 HERNAN ARREOLA
Applicant returned to address corrections 8/20/2021 CARLOS MONTES
Plan Check Approved 10/28/2021 CARLOS MONTES
Issued 2/17/2022 APPLICANT
CofO in Progress 8/14/2024 CRAIG DAVIS
Permit Finaled 9/3/2024 RUBEN SALAS
CofO Issued 9/3/2024 RUBEN SALAS
Permit Finaled 9/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/13/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 7/13/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/28/2021 JEANIE LAM
Sewer availability Cleared 7/28/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/25/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 5/13/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 5/31/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Approved ENRIQUE MIRELES
Green Building Rough 6/14/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 6/28/2022 Approved ENRIQUE MIRELES
HVAC-Rough 6/28/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 6/28/2022 Approved ENRIQUE MIRELES
Insulation 7/13/2022 Approved ENRIQUE MIRELES
Drywall Nailing 8/4/2022 Approved ENRIQUE MIRELES
Sewer 12/21/2022 No Access for Inspection ENRIQUE MIRELES
Shower Pan 12/21/2022 No Access for Inspection ENRIQUE MIRELES
Gas Test 12/27/2022 No Access for Inspection ENRIQUE MIRELES
Sewer 12/27/2022 No Access for Inspection ENRIQUE MIRELES
Shower Pan 12/27/2022 No Access for Inspection ENRIQUE MIRELES
Sewer 3/1/2023 Not Ready for Inspection ENRIQUE MIRELES
Shower Pan 3/1/2023 Approved ENRIQUE MIRELES
Sewer 3/29/2023 Corrections Issued ENRIQUE MIRELES
Gas Test 4/5/2023 Approved ENRIQUE MIRELES
Sewer 4/5/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 7/28/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 7/28/2023 Approved ENRIQUE MIRELES
Final 7/28/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 7/28/2023 Approved ENRIQUE MIRELES
HVAC-Final 7/28/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 7/28/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 7/28/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 8/18/2023 Approved ENRIQUE MIRELES
Final 8/18/2023 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 8/18/2023 Corrections Issued ENRIQUE MIRELES
Final 8/31/2023 Corrections Issued ENRIQUE MIRELES
HVAC-Final 9/5/2023 Approved ENRIQUE MIRELES
Final 5/21/2024 Corrections Issued CRAIG DAVIS
Final 6/25/2024 Partial Approval CRAIG DAVIS
Final 7/3/2024 Corrections Issued CRAIG DAVIS
Final 8/13/2024 OK to Issue CofO CRAIG DAVIS
Service/Power Release 8/13/2024 Approved CRAIG DAVIS