13554 W PIERCE ST 91331

Certificate Information: 13554 W PIERCE ST 91331

Application / Permit
21014-10000-01930
Plan Check / Job No.
B21LA07221
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED BEDROOM, BATHROOM AND CLOSET ADDITION AT REAR OF (E) SFD. INCLUDES CONVERTING CLOSET TO FULL BATHROOM. CONST. PER W.F.P.P.
Permit Issued
Issued on 7/14/2021
Issuing Office
Current Status
CofO Issued on 4/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2021 APPLICANT
Assigned to Plan Check Engineer 4/23/2021 LAWRENCE QUIRANTE
Corrections Issued 4/24/2021 LAWRENCE QUIRANTE
Building Plans Picked Up 5/3/2021 APPLICANT
Plan Check Approved 5/25/2021 LAWRENCE QUIRANTE
Issued 7/14/2021 APPLICANT
CofO in Progress 4/14/2022 MICHEL ABAJAN
Permit Finaled 4/18/2022 RONALD MYRICK
CofO Issued 4/18/2022 RONALD MYRICK
Permit Finaled 4/18/2022 RONALD MYRICK

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/10/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/18/2021 GABRIEL ROBLES
Sewer availability Cleared 5/18/2021 GABRIEL ROBLES

Contact Information

Architect , ; Lic. No.: C35683       ,
Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/18/2021 Partial Approval MICHEL ABAJAN
Sewer 8/18/2021 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 9/2/2021 No Access for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 9/7/2021 Approved JENNIFER RABUCHIN
METHANE-Barrier 9/7/2021 Approved JENNIFER RABUCHIN
METHANE-Rough 9/7/2021 Approved JENNIFER RABUCHIN
METHANE-Subgrade 9/7/2021 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/5/2021 Partial Approval MICHEL ABAJAN
Deputy Wood Construction 10/19/2021 No Access for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 10/20/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 10/20/2021 Approved MICHEL ABAJAN
Green Building Rough 10/20/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 10/20/2021 Approved MICHEL ABAJAN
Insulation 10/25/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/25/2021 Approved MICHEL ABAJAN
Drywall Nailing 10/29/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 10/29/2021 Approved JESUS RODRIGUEZ
Shower Pan 10/29/2021 Approved JESUS RODRIGUEZ
Final 12/15/2021 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 12/15/2021 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/15/2021 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 12/15/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/9/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 2/9/2022 Approved MICHEL ABAJAN
Final 2/9/2022 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 2/9/2022 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 2/9/2022 Approved MICHEL ABAJAN
Drywall Nailing 2/22/2022 Approved KRISTEN CAUSEY
ELECTRICAL-Final 4/14/2022 Approved MICHEL ABAJAN
Final 4/14/2022 OK to Issue CofO MICHEL ABAJAN
Green Building Final 4/14/2022 Approved MICHEL ABAJAN
HVAC-Final 4/14/2022 Approved MICHEL ABAJAN
PLUMBING-Final 4/14/2022 Approved MICHEL ABAJAN