238 E 91ST ST 90003

Certificate Information: 238 E 91ST ST 90003

Application / Permit
21014-10000-01925
Plan Check / Job No.
B21LA07196
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION AND ADDITION TO (E) GARAGE TO CREATE DETACHED ACCESSORY DWELLING UNIT. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS. Per LAMC 12.22 A.33(c)(d) **UPDATE ADDRESS PENDING BOE CLEARANCE**
Permit Issued
Issued on 1/25/2022
Issuing Office
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 GEORGE ALVAREZ
Corrections Issued 4/29/2021 GEORGE ALVAREZ
Plan Check Approved 1/1/2022 KHUONG TRUONG
Issued 1/25/2022 APPLICANT
Building Plans Picked Up 1/28/2022 APPLICANT
CofO in Progress 1/17/2023 LILIANA PORTILLO
Permit Finaled 1/19/2023 DEROLD HAUFF
CofO Issued 1/19/2023 DEROLD HAUFF
Permit Finaled 1/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/21/2021 JEANIE LAM
Sewer availability Cleared 5/24/2021 JEANIE LAM
Low Impact Development Cleared 10/19/2021 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 10/20/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 10/20/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/24/2022 Partial Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 6/6/2022 Approved LILIANA PORTILLO
Footing/Foundation/Slab 6/6/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 7/22/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 7/22/2022 Approved ENRIQUE MIRELES
Green Building Rough 7/22/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 7/22/2022 Approved ENRIQUE MIRELES
Insulation 8/16/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 8/16/2022 Corrections Issued LILIANA PORTILLO
Drywall Nailing 9/7/2022 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 9/7/2022 Approved LILIANA PORTILLO
Sewer 9/7/2022 Approved LILIANA PORTILLO
Underground Mechanical 9/7/2022 Partial Approval LILIANA PORTILLO
Drywall Nailing 9/14/2022 Approved LILIANA PORTILLO
Underground Mechanical 10/19/2022 Conditional Approval SCOTT FINNILA
ELECTRICAL-Final 12/15/2022 Approved LILIANA PORTILLO
Final 12/15/2022 Corrections Issued LILIANA PORTILLO
Gas Test 12/15/2022 Approved LILIANA PORTILLO
Green Building Final 12/15/2022 Corrections Issued LILIANA PORTILLO
HVAC-Final 12/15/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 12/15/2022 Approved LILIANA PORTILLO
Smoke Detectors 12/15/2022 Approved LILIANA PORTILLO
Final 1/10/2023 Conditional Approval LILIANA PORTILLO
Green Building Final 1/10/2023 Approved LILIANA PORTILLO
HVAC-Final 1/10/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/10/2023 SGSOV Approved LILIANA PORTILLO
Service/Power Release 1/10/2023 Approved LILIANA PORTILLO