2642 S CLYDE AVE 90016

Certificate Information: 2642 S CLYDE AVE 90016

Application / Permit
21014-10000-01922
Plan Check / Job No.
B21LA07194
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (100 SF) AND CONVERT PORTION OF EXISTING GARAGE TO ADU (88 SF) PER CA GOVT. CODE 65852.2(e)(1) AND APPLICABLE PART OF LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 9/9/2021
Issuing Office
Current Status
CofO Issued on 6/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 SERGIO GUTIERREZ
Corrections Issued 5/4/2021 SERGIO GUTIERREZ
Quality Review Completed 5/6/2021 FARUK SEZER
Applicant returned to address corrections 8/10/2021 SERGIO GUTIERREZ
Plan Check Approved 9/9/2021 SERGIO GUTIERREZ
Issued 9/9/2021 APPLICANT
Building Plans Picked Up 9/14/2021 APPLICANT
CofO in Progress 6/2/2023 JOSE AVILA
Permit Finaled 6/3/2023 DEROLD HAUFF
CofO Issued 6/3/2023 DEROLD HAUFF
Permit Finaled 6/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/18/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 5/18/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 5/19/2021 RENZ SORIANO
Sewer availability Cleared 5/19/2021 RENZ SORIANO
Hydrant and Access approval Cleared 8/13/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Banning,, George Kwame; Lic. No.: C53074 7550 LILY COURT      FONTANA, CA 92336

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/1/2021 Corrections Issued JOSE AVILA
Underground Mechanical 1/19/2022 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 1/25/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 1/25/2022 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 1/28/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 4/4/2022 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 4/4/2022 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Approved JOSE AVILA
Green Building Rough 4/4/2022 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 4/4/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 4/13/2022 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 4/13/2022 Corrections Issued JOSE AVILA
Green Building Rough 4/13/2022 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 4/26/2022 Approved JOSE AVILA
ELECTRICAL-Rough 4/26/2022 Approved JOSE AVILA
Green Building Rough 4/26/2022 Approved JOSE AVILA
HVAC-Rough 4/26/2022 Approved JOSE AVILA
Interior/Exterior Lathing 8/17/2022 Approved JOSE AVILA
Insulation 8/23/2022 Approved JOSE AVILA
Shower Pan 8/23/2022 Approved JOSE AVILA
Drywall Nailing 10/12/2022 Corrections Issued JOSE AVILA
Drywall Nailing 10/20/2022 Approved JOSE AVILA
HVAC-Final 4/26/2023 Partial Inspection JOSE AVILA
ELECTRICAL-Final 5/8/2023 Approved JOSE AVILA
Footing/Foundation/Slab 5/8/2023 Approved JOSE AVILA
Green Building Final 5/8/2023 Corrections Issued JOSE AVILA
PLUMBING-Final 5/8/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 5/8/2023 SGSOV Not Ready JOSE AVILA
Smoke Detectors 5/8/2023 Approved JOSE AVILA
HVAC-Final 5/12/2023 Corrections Issued JOSE AVILA
Final 5/18/2023 Partial Inspection JOSE AVILA
Green Building Final 5/18/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 5/18/2023 SGSOV Approved JOSE AVILA
Service/Power Release 5/18/2023 Approved JOSE AVILA
Final 6/2/2023 OK to Issue CofO JOSE AVILA